Steel sheet pile cofferdam construction process

A steel sheet pile cofferdam and construction technology, which is applied to sheet pile walls, foundation structure engineering, construction, etc., can solve the problem of poor anti-scourability of the water side of the cofferdam, inability to compact underwater fill, and large amount of steel sheet piles To achieve the effect of reducing the workload of protection and anti-seepage, shortening the construction period and speeding up the construction progress

Inactive Publication Date: 2021-06-25
CHINA RAILWAY 16TH BUREAU GRP CO LTD
View PDF4 Cites 3 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

The existing bagged sand cofferdam structure mainly has the following disadvantages: the section of the cofferdam is large, which occupies the river channel and affects the discharge; the underwater fill cannot be compacted, and the reliability is low; Difference
The steel sheet pile cofferdam structure, compared with the bagged sand cofferdam structure, has a smaller cofferdam section, and has better anti-seepage effect and anti-scouring performance, but the conventional steel sheet pile cofferdam structure is double-row continuous arrangement, the steel plate The amount of piles is large; the steel sheet piles need to be equipped with steel tie rods, and the steel tie rods generally need to be pulled manually on board, which is difficult to construct

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Steel sheet pile cofferdam construction process

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0024] The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

[0025] see figure 1 , a steel sheet pile cofferdam construction process, comprising the following steps:

[0026] Step 1. Preparation before construction, inspection and repair of steel sheet piles: After loading, unloading and transportation, steel sheet piles often have trauma, bending and locking deformation, and steel sheet piles must be inspected; check the vibratory hammer;

[0027] Step 2: Drive the guide piles into the construction. Before inserting a...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a steel sheet pile cofferdam construction process. The steel sheet pile cofferdam construction process comprises the steps of preparation before construction, guide pile driving construction, steel sheet pile inserting and driving construction, steel sheet pile folding construction, inner support installation, seepage-proofing and leakage-stopping treatment and bottom sealing concrete. The steel sheet pile cofferdam construction process has the beneficial effects that the side pressure of a soil body in a cofferdam to steel sheet piles is reduced through the steel sheet pile cofferdam mode, the pile length is properly decreased, and compared with a traditional cofferdam structure, the steel sheet pile consumption is greatly reduced; due to the fact that the steel sheet piles are located on the water side of the cofferdam, overwater driving and pulling are convenient, the construction difficulty of cofferdam engineering is effectively lowered, the cofferdam construction quality is improved, the construction progress is accelerated, and the construction period is shortened; and the steel sheet piles have a good seepage-proofing effect and good anti-scouring performance, compared with a traditional earth-rock cofferdam, the cofferdam upstream face protection and seepage-proofing workload can be greatly reduced, and the steel sheet pile cofferdam structure has better adaptability and feasibility.

Description

technical field [0001] The invention relates to a steel sheet pile cofferdam, in particular to a steel sheet pile cofferdam construction process, which belongs to the technical field of building construction. Background technique [0002] For water conservancy and hydropower projects, water transport and port projects, municipal engineering and civil construction projects built near the water, construction cofferdams for retaining water must be installed before construction to form foundation pits for dry land construction. Currently commonly used cofferdam structures include earth-rock cofferdam structure, bagged soil cofferdam structure, bagged sand cofferdam structure and double-row steel sheet pile frame cofferdam structure. The existing bagged sand cofferdam structure mainly has the following disadvantages: the section of the cofferdam is large, which occupies the river channel and affects the discharge; the underwater fill cannot be compacted, and the reliability is lo...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E02D19/04E02D5/04E02D5/06
CPCE02D19/04E02D5/04E02D5/06
Inventor 王萍刘博丁传峰孙成龙
Owner CHINA RAILWAY 16TH BUREAU GRP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products