A technology of waffle boards and column caps, which is applied in the field preparation of formwork/formwork/work frames, building components, construction, etc., and can solve the problem of high steel content per unit space of the frame and heavy weight of the primary and secondary corrugations. , Low installation efficiency of primary and secondary flute, etc., to achieve the effect of shortening the installation period, simple structure design, and high construction efficiency
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0031] The support system of the waffle plate column cap lower plate buckle type steel pipe and rectangular steel pipe formwork includes wooden formwork, rectangular double steel pipe plus wooden square and steel pipe combined secondary flute, rectangular single steel pipe main flute, adjustable support, and buckle type Steel formwork support, adjustable base. Specifically, the 1m thick waffle plate column cap formwork system from top to bottom consists of 15mm thick wood formwork, 50*100*3mm rectangular double steel pipes plus 50*80mm wooden squares and 48mm ordinary steel pipe combined secondary flute, 50*100*3mm Rectangular single steel pipe main flute, 600mm adjustable support, 48mm series buckle steel pipe support formwork, 500mm adjustable base consists of six parts.
[0032] see now Figure 1-Figure 3 , figure 1 It is a plan view of the column cap structure of the embodiment of the present invention, figure 2 It is a plan view of the column cap structure of the embo...
Embodiment 2
[0042] The procedure for setting up the formwork system of the buckle-type steel pipe under the waffle plate column cap and the formwork support system of the rectangular steel pipe of the present invention is as follows: adjustable base→vertical pole→horizontal bar→adjustable top support→primary corrugation→secondary corrugation→formwork.
[0043] The construction steps of the buckle-type steel pipe under the waffle plate column cap of the present invention and the formwork support system of the rectangular steel pipe:
[0044] 1. Find out the center line of the column, determine the position of the six poles at the bottom of the column cap according to the plan of the pole, and place the adjustable base.
[0045] 2. Assemble the poles and crossbars of the buckle-type frame. The distance between the poles is 1.2m, which is consistent with the distance between the poles under the waffle board. A pole is added on the east and west sides of the column cap. The height is different a...