High fill subgrade connection method
A high fill and roadbed technology, applied in the directions of roads, roads, buildings, etc., can solve the problems of insignificant reduction in the amount of foundation treatment, it is difficult to ensure that the old pavement does not crack, and the driving safety is affected, so as to save the construction period, The effect of saving arable land resources and clear force
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Example Embodiment
[0026] Example 1
[0027] image 3 Shown is the method for splicing new and old roadbeds by setting up an inclined retaining wall on the upper slope. It is to carry out digging and pouring concrete pile treatment and supporting structure construction near the upper 8m platform of the high fill. That is, the old roadbed 1 is excavated longitudinally on the side slope of the old roadbed 1 according to the inner slope rate of the supporting structure, and the slope is supported 13 to ensure the stability of the slope, and then the bored pile 12 is constructed according to the conventional method. The pile diameter is generally 0.8 to 1.6 meters, and the pile length and longitudinal pile spacing need to be determined in accordance with the bearing capacity requirements of the supporting structure. The conventional pile side friction resistance and cone tip resistance meet the bearing capacity requirements. The longitudinally isolated bored cast-in-place piles 12 are connected to the...
Example Embodiment
[0035] Example 2
[0036] Figure 4 Shown is the method of setting up a counterweight retaining wall on the upper slope to rewind the new and old subgrade. This is on the basis of the scheme of Embodiment 1. Due to the larger volume of the counterweight retaining wall, more excavation of the old roadbed 1 is required. Therefore, in order to ensure the stability of the excavation of the old roadbed 1, it is necessary to lay a 20-28mm diameter anchor rod on the slope to be excavated before excavation, and the top of the anchor rod exposes the steep slope 5cm on the inner side of the retaining wall. After excavating the old roadbed from top to bottom with slope rate, the anchor rod head hanging diameter ≥8mm, mesh size 20x20cm reinforced mesh and spraying 8~10cm C20 concrete support plan immediately exposed on the excavated slope surface will ensure During the construction of the retaining wall, the slope surface is stable, and after the foundation treatment is qualified, the grave...
Example Embodiment
[0037] Example 3
[0038] Figure 5 Shown is the method of splicing new and old roadbeds by setting up buttressed retaining walls on the upper slope. It is based on the schemes of Example 1 and Example 2, and the construction of C25 reinforced concrete buttress retaining wall 9 is carried out. Due to the light weight of the retaining wall, the requirement for the foundation bearing capacity is relatively low, and the amount of foundation treatment under the wall bottom plate is less than that of Examples 1 and 2. Steep slope excavation and support are the same as in Example 2, and the others are the same as in Example 1.
PUM
Property | Measurement | Unit |
---|---|---|
Thickness | aaaaa | aaaaa |
Particle size | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap