Subway track bed reinforcement construction process
A construction technology and technology of ballast bed, applied in the directions of roads, tracks, laying tracks, etc., can solve the problems of increasing the number of drilling holes, deformation of the track bed, and increasing the amount of slurry poured in, reducing the number of drilling holes, simplifying the construction process, The effect of saving construction time
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0016] Small-scale drilling equipment is used to drill holes of Φ40mm on the ballast bed, and the hole depth enters the second lining, with a depth of 40cm; the drill holes are arranged in two rows, in a plum blossom shape, with a hole spacing of 1.0m and a row spacing of 2.0m; The length and hole depth of the hollow anchor with grouting joints should make the length of the anchor 5cm longer than the actual hole depth. Then lower the hollow anchor rod connected with the grouting joint into the hole; pre-tighten the rod body so that the top of the anchor head and the bottom of the hole are tightly locked, and then install the grout stopper, backing plate and nut. After the connection, use a wrench to implement prestressed tension and mechanical locking. Prepare the modified epoxy resin grouting material and pour it into the grouting machine; start the grouting machine for grouting, and finish grouting when the grouting volume is less than 0.03L / min after the pressure reaches 0....
Embodiment 2
[0018] Small-scale drilling equipment is used to drill holes of Φ38mm on the ballast bed. The depth of the hole is 86cm when it enters the primary branch; The length and hole depth of the hollow bolt with grouting joints should make the length of the bolt 4cm longer than the actual hole depth. Then lower the hollow anchor rod connected with the grouting joint into the hole; pre-tighten the rod body so that the top of the anchor head and the bottom of the hole are tightly locked, and then install the grout stopper, backing plate and nut. After the connection, use a wrench to implement prestressed tension and mechanical locking. Prepare the cement grouting material and pour it into the grouting machine; start the grouting machine for grouting, and when the pressure reaches 0.6MPa and the grouting amount is less than 0.05L / min, the grouting ends. Seal the holes and clean the equipment.
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com