A high-concentration water and coal-upgrading technology, which is applied in the direction of combustion methods, block/powder fuel preparation, combustion equipment, etc., can solve the problems that it cannot be used as boiler fuel and coal gasifier raw material, and has not made breakthrough progress, etc. Achieve the effects of excellent performance, low production cost and simple process
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0023] Example 1, lignite is pre-broken to below 10mm, the drying temperature is controlled at 150°C in a gauge pressure of 0-0.1MPa and an inert gas environment, the heating rate is at 100-150°C / s, and the residence time is controlled at 40min. After drying Coal is pyrolyzed at medium temperature, the reaction temperature is controlled at 750°C, the heating rate is 100-500°C / s, and the residence time is controlled at 20min. The upgraded coal after cooling uses a ball mill to grind coal for sample preparation. The diameter ratio of the steel balls is 20mm, 12mm and 5mm, and the mass ratio is 20%:50%:30%. The ball mill speed is set at 170r / min. Coal time 3min. The coal samples were sieved with a 1mm sieve, and the coal samples smaller than 1mm were mixed with water evenly, and then stirred with a stirrer with a rotation speed of 1000r / min for 18min, and finally the coal water slurry samples of the examples were prepared. The results are shown in Table 3.
Embodiment 2
[0024] Example 2, the lignite is pre-broken to less than 10mm, the drying temperature is controlled at 280°C under normal pressure and an inert gas environment, the heating rate is 100-150°C / s, the residence time is controlled at 35min, and the dried coal is subjected to medium-temperature pyrolysis , the reaction temperature is controlled at 620°C, the heating rate is at 100-500°C / s, and the residence time is controlled at 25min. The upgraded coal after cooling uses a ball mill to grind coal for sample preparation. The diameter ratio of the steel balls is 20mm, 12mm and 5mm, and the mass ratio is 20%:50%:30%. The ball mill speed is set at 170r / min. Coal time 3min. Coal samples were sieved with a 1mm sieve, and water and additives (lignin, used in an amount of 0.3% of the upgraded coal, wt) were added to coal samples smaller than 1mm and mixed evenly, and then stirred for 15 minutes with a stirrer at a speed of 1000r / min, and finally prepared Become embodiment coal water slur...
Embodiment 3
[0025] Example 3, lignite is pre-broken to less than 10mm, the drying temperature is controlled at 300°C under normal pressure and an inert gas environment, the heating rate is 100-150°C / s, the residence time is controlled at 30min, and the dried coal is subjected to medium-temperature pyrolysis , the reaction temperature is controlled at 600°C, the heating rate is at 100-500°C / s, and the residence time is controlled at 30min. The upgraded coal after cooling uses a ball mill to grind coal for sample preparation. The diameter ratio of the steel balls is 20mm, 12mm and 5mm, and the mass ratio is 20%:50%:30%. The ball mill speed is set at 170r / min. Coal time 3min. Coal samples were sieved with a 1mm sieve, and water and additives were added to coal samples smaller than 1mm (ZM-19 high-efficiency coal-water slurry additive, produced by Changzhou Zhongnan Chemical Co., Ltd., with lignin as the main raw material, and the dosage was 0.3% of the upgraded coal, wt) and mix evenly, the...