Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Compaction construction method of lower arc position of sandy soil basement drain pipe

A construction method and technology for drainage pipes, which are applied to the sewer system, waterway system, water supply device, etc., can solve the problems of road surface collapse, the backfill density of the arc under the drainage pipe is difficult to meet the design requirements, etc. Uniformity, avoiding road collapse, and strong applicability

Active Publication Date: 2016-03-09
SCEGC MECHANIZED CONSTR GRP COMPANY
View PDF4 Cites 1 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] The purpose of the present invention is to provide a compact construction method for the circular arc under the drainage pipe on a sandy soil base, which is used to solve the problem that the backfill density of the circular arc under the drainage pipe is difficult to meet the design requirements, and completely solve the problem of road surface subsidence

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Compaction construction method of lower arc position of sandy soil basement drain pipe
  • Compaction construction method of lower arc position of sandy soil basement drain pipe
  • Compaction construction method of lower arc position of sandy soil basement drain pipe

Examples

Experimental program
Comparison scheme
Effect test

Embodiment

[0044] A municipal road has a length of 401.321m and a planned red line width of 50m. The road grade is the main road of the city, and the bottom of the rainwater and sewage ditch is a thick sand layer with good water permeability. The diameter of the rainwater pipe is di800mm, the excavation width at the bottom of the trench is 1800mm, and a 500mm working face is left on both sides of the pipe; the working face is narrow. The diameter of the sewage pipe is di500mm, the excavation width at the bottom of the trench is 1300mm, and 400mm of working face is left on both sides of the pipe. The original ground elevation: 390.3m, the depth of the trench is 2.7m-4m, and the slope is 0.3%. The upper part of the trench is collapsible loess, and the lower part is sandy soil. The drainage pipe is made of steel belt reinforced polyethylene (PE) spiral corrugated pipe, which is laid at the bottom of the pipe trench whose bearing capacity meets the design requirements. The design requires ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a compaction construction method of a lower arc position of a sandy soil basement drain pipe. The method includes the following steps of laying the drain pipe for a closed-water test; laying a drain pipeline on a pipe ditch central line, conducting a closed-water test on the drain pipeline, and conducting pipe ditch backfill work after the closed-water test is qualified; conducting layered backfill sand laying and cofferdam forming; mechanically or manually putting sandy soil to the two sides of a pipeline in a ditch, and manually spreading sandy soil to be uniform; building a cofferdam 300 mm wide and 300 mm high every 10 mm, and conducting water injecting; conducting water injecting work on the two sides of the drain pipe at the same time after a sandy layer is laid completely; conducting grinding through a spike grinder, and conducting sand compensating, wherein grinding is conducted through the spike grinder, the number of grinding times is not smaller than 8, and the lap joint width in the grinding process is not smaller than one third of the width of the grinder; grinding reserved holes and conducting manual filling and compacting after grinding is completed; detecting compactness and conducting acceptance; detecting sandy soil compactness after water completely permeates the sandy layer, and conducting backfill work of the next layer till the backfill standard height meets the design requirement after the design requirement is met.

Description

Technical field: [0001] The invention relates to the technical field of outdoor public drainpipe construction, in particular to a construction method for dense construction at the circular arc under a sandy soil base drainpipe. Background technique: [0002] In recent years, road subsidence accidents have occurred frequently due to continuous rain, causing a lot of economic and property losses and seriously affecting the smooth flow of roads. It has aroused widespread concern from society and construction units. Pipeline leakage is the main factor causing urban road pavement subsidence. The reason is that in the process of backfilling the pipe trench, the backfilling at the bottom of the pipe is not compact, resulting in uneven settlement of the foundation, which causes the pipe to rupture. After the underground drainage pipeline leaks, the water content of the subgrade will increase, the bearing capacity will decrease, and the road surface will collapse under the action o...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E03F3/06
CPCE03F3/06
Inventor 汪东兵缑百强张怀勤王宝生任国钊张飞强
Owner SCEGC MECHANIZED CONSTR GRP COMPANY
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products