A construction method and technology of steel-jacketed box, which can be applied in basic structure engineering, construction and other directions, can solve the problems of unfavorable demolition and demolition, waste of materials, insufficient rigidity of cofferdam, and achieve easy demolition and demolition, simple construction process, The effect of reducing the amount of use
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0031] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.
[0032] The embodiment of the present invention provides a method for constructing a cofferdam of a double-wall locking steel casing, which specifically includes the following steps:
[0033] A. The inner support 3 of the top layer, the inner support 4 of the bottom layer and the connection system 12 for connecting the inner support 3 of the top layer and the inner support 4 of the bottom layer, a number of cofferdam side plates 1 and the same number of cofferdam side plates 1 for connecting the cofferdam The water-stop locking piles 2 of the weir side plate 1 are all transported to the target pier position.
[0034] One side of each cofferdam side plate 1 is welded with a first steel pipe 7, and the opposite side is welded with a second steel pipe 10, the pipe wall of the first steel pipe 7 has a first gap along the height direction, ...