Fast and highly-efficient tunneling method for large section of hard-rock tunnel in coal mine by combination of fully-mechanized tunneling and blasting driving

A large-section, hard-rock technology, which is applied to the field of fast and efficient excavation of large-section hard rock roadways in coal mines, can solve the problems of inability to excavate normally, affect the speed and efficiency of hard rock artillery excavation, and reduce the effect of fully mechanized excavation, and achieve the drilling workload. And the effect of reducing time, reducing the amount of single detonating charge, and increasing the speed of tunnel excavation

CN105937395AActive Publication Date: 2016-09-14湖南省煤业集团红卫矿业有限公司
9 Cites 15 Cited by

Patent Information

Authority / Receiving Office
CN · China
Current Assignee / Owner
Publication Date
2016-09-14

Smart Images

  • Figure 1
    Figure 1
  • Figure 2
    Figure 2
  • Figure 3
    Figure 3
Patent Text Reader

Abstract

The invention relates to a fast and highly-efficient tunneling method for a large section of a hard-rock tunnel in a coal mine by combination of fully-mechanized tunneling and blasting driving. As shown in the figure 1, a cut hole with the borehole diameter of Phi 40.0 mm and a reliever hole with the charge diameter of Phi 35.0 mm are arranged in the section of the hard-rock tunnel with the protodyakonov coefficient f larger than 10.0 for digging out a groove cavity with s approximately equal to 14.0 m<2>. As shown in the figure 2, the cut hole adopts a three-stage oblique cut with stages deepening and angles of inclination increasing stage by stage. The consumption of charge in unit volume is determined based on the hard-rock protodyakonov coefficient and shot hole depth according to quantification of the figure 3. Three stages of oblique cuts respectively select I, III, IV-section millisecond delay detonators. A V-section millisecond delay detonator is selected by the reliever hole. The oblique cuts and the whole section of the reliever hole are detonated once with the total delay time no more than 130.0ms. After the groove cavity is formed in a blasting method. The reasonable tooth parameters are selected to rapidly expand the groove cavity to the design section and contour is finished under effect of a free surface of a fully-mechanized coal winning machine. Due to millisecond delay detonation of the oblique cut in three stages and larger borehole diameter, stemming is blocked to increase so that rocks do not affect the fully-mechanized coal winning machine after the working surface during the throwing process. The safe and efficient effect can be achieved.
Need to check novelty before this filing date? Find Prior Art

Description

technical field

[0001] The patent of the present invention relates to a fast and efficient tunneling method for a large-section hard rock roadway in a coal mine, in particular to a method for fast and efficient tunneling of a large-section hard rock roadway in a coal mine by combining mechanized excavation and blasting excavation. Background technique

[0002] Mechanized excavation is widely used in roadway excavation due to its fast excavation speed and high excavation efficiency. However, for rocks with high hardness, the advantages are not obvious. For hard rocks, the excavation speed and efficiency are significantly reduced or even cannot be excavated normally. Engineering practice shows that: when the rock Platts coefficient f<6.0, the effect of fully-mechanized excavation is obvious; when f=6.0-8.0, the speed and efficiency of fully-mechanized excavation will be reduced; At 10.0, because the cutter teeth cannot form notches in the roadway section, it is almost impos...

Examples

Embodiment Construction

[0016] picture 2 Blasting for Excavating Cavity I by Blasting picture Table: The layout of the blast hole is divided into two parts, the cutting hole and the auxiliary hole. The cutting hole is divided into three levels of cutting, and each level of cutting is gradually deepened, and the inclination angle is gradually increased. , That is, the millisecond detonator of section I is selected for the first-level cut, the millisecond detonator of section III is selected for the second-level cut, and the millisecond detonator of section IV is selected for the third-level cut. The charge consumption per unit volume of the eye is determined according to the charge consumption per unit volume and the blasting rock volume borne by each blasthole. The detonation is delayed for a period of milliseconds, and the total delay is about 100.0ms, not exceeding 130.0ms. In order to fully break the rock and ensure sufficient mud plugging length, the currently commonly used Φ32.0mm small-dia...