Deck type arch bridge vault padding unloading and reinforcing construction method and application
A construction method and technology for arch bridges, applied in bridge reinforcement, arch bridges, bridges, etc., can solve problems such as bridge collapse, changes in design linearity and pressure line, and unbalanced construction and unloading.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0022] A construction method for unloading and reinforcing construction of an upward arch bridge vault filling, which comprises the following steps:
[0023] (1) Divide the bridge deck into an odd number of working faces from the center of the bridge deck to both sides according to the length direction of the bridge, and the width of each working face is 1000㎜~3000㎜;
[0024] (2) First excavate the central working face of the bridge deck, unload the bridge deck pavement and vault filling, clean the arch back, and repair the main arch ring and abdominal arch diseases with grout;
[0025] ⑶ Then backfill the excavation surface with plain concrete for the vertical formwork;
[0026] ⑷Concrete backfill curing, so that the strength reaches the design strength of 65﹪~75﹪;
[0027] (5) Excavate the working faces on both sides of the central working face in turn, and construct according to the construction process and requirements of the central working face until the construction of...
Embodiment 2
[0038] This embodiment is a double-curved arch bridge. The main bridge is a catenary double-curved arch bridge with equal cross-section of 2×40m (net). The arch ribs and vaults of the arch circle are all cracked, and 60% of the main arch circle enters the tension zone. The substructure is a masonry gravity-type abutment, and the bridge deck is a mud-bound gravel pavement. Depend on image 3 It can be seen that when repairing and strengthening the bridge deck, the bridge deck is divided into seven working faces from the center of the bridge deck to both sides according to the length direction of the bridge, namely, the central working face 1, the second working face 2, the third working face 3, and the fourth working face. Working face 4, fifth working face 5, sixth working face 6 and seventh working face 7, in which the central working face 1 has a width of 3.0m, the second working face 2, the third working face 3, and the fourth working face 4 , The widths of the fifth worki...
PUM
Property | Measurement | Unit |
---|---|---|
Diameter | aaaaa | aaaaa |
Length | aaaaa | aaaaa |
Diameter | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com