Method for reducing membrane blocking and removing phosphorus in MBR (Membrane Bioreactor) by utilizing sludge of water treatment plant
A technology for waterworks and reactors, applied in the field of membrane clogging and phosphorus removal, can solve the problems of ineffective biological phosphorus removal and membrane clogging, and achieve the effects of low cost, reduced membrane clogging and simple operation
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
example 1
[0021] A method for reducing membrane clogging and phosphorus removal in an MBR reactor by using sludge from a waterworks plant, comprising the steps of:
[0022] (1) Take sludge from waterworks;
[0023] (2) Take an integrated MBR reactor that operates normally but has a certain degree of membrane clogging, the effective volume of the reactor is 21L, and the membrane flux is 35L / m 2 / h, TP is 10mg / L continuous aeration, and the influent is configured sewage;
[0024] (3) Add the sludge from the waterworks described in step (1) into the reactor once per day in an amount of 100 mg / L. After 30 days of stable operation, aerobic granular sludge is obtained in the reactor, and membrane clogging is reduced. , Membrane flux becomes 40L / m 2 / h, TP in the reactor is 1mg / L.
example 2
[0026] A method for reducing membrane clogging and phosphorus removal in an MBR reactor by using sludge from a waterworks plant, comprising the steps of:
[0027] (1) Take sludge from waterworks;
[0028] (2) Take an integrated MBR reactor that operates normally but has a certain degree of membrane clogging, the effective volume of the reactor is 21L, and the membrane flux is 30L / m 2 / h, TP is 10mg / L continuous aeration, and the influent is configured sewage;
[0029] (3) The sludge from the waterworks described in step (1) is added to the reactor at one time at an addition rate of 500 mg / L per day. After 14 days of stable operation, aerobic granular sludge is obtained in the reactor, and the membrane clogging is reduced. , membrane flux becomes 45L / m 2 / h, TP in the reactor is 0.8mg / L.
example 3
[0031] A method for reducing membrane clogging and phosphorus removal in an MBR reactor by using sludge from a waterworks plant, comprising the steps of:
[0032] (1) Take sludge from waterworks;
[0033] (2) Take an integrated MBR reactor that operates normally but has a certain degree of membrane clogging, the effective volume of the reactor is 21L, and the membrane flux is 35L / m 2 / h, TP is 10mg / L continuous aeration, and the influent is configured sewage;
[0034] (3) Add the sludge from the waterworks described in step (1) to the reactor once per day in an amount of 1000 mg / L. After 10 days of stable operation, aerobic granular sludge is obtained in the reactor, and membrane clogging is reduced. , Membrane flux becomes 48L / m 2 / h, TP in the reactor is 0.3mg / L.