Integrated drilling and hole forming method for pile body and pile cap of drilled grouting pile
A technology for bored cast-in-place piles and pile caps, which is applied to drilling equipment and methods, impact drilling, rotary drilling, etc., can solve the problems of long construction time, high cost, and many processes, and achieve a simple construction method. , installation and use of simple operation, strong operability effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0066] Such as figure 1 A bored cast-in-place pile and a pile cap are shown as an integrated drilling and hole-forming method. The bored pile constructed includes a pile body 16 and a pile cap 17 coaxially arranged on the top of the pile body 16. The pile body 16 and pile cap 17 are connected as a whole and the cross section of both is circular, and described pile cap 17 and pile body 16 are all arranged vertically; The diameter of described pile body 16 is all the same from bottom to top, see for details Figure 10 ;
[0067] The following steps are included in the integrated drilling of the pile body and the pile cap to form the bored pile:
[0068] Step 1, pile cap construction device processing: according to the diameter of the pile body 16 and the pile cap 17 and the height of the pile cap 17 in the drilled cast-in-place pile, the pile cap construction device is processed;
[0069] Such as figure 2 , Image 6 As shown, the pile cap construction device includes a pile...