Squeeze-spraying reaming press-grouting concrete pile and construction method thereof and drilling machine
A technology for pouring concrete and a construction method, which is applied in earth-moving drilling, drilling equipment and methods, and drilling with liquid/gas jets, etc., can solve the problem of ineffective formation of skeleton structure, reduction of concrete pile bearing capacity, and damage of stratum skeleton structure. and other problems, to achieve the effect of low hardness, low energy consumption, and low torque required for power
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0043] combine Figure 1-5 Shown, a kind of extruding and spraying reaming pressure grouting concrete pile drilling rig, comprises the helical hollow drill rod that is combined by a plurality of split drilling tools, the power head 5 that is connected with helical hollow drill rod, the core tube of helical hollow drill rod A high-pressure grouting pipe 4 is installed on one side of the outer wall or the inner wall from top to bottom. The upper end of the high-pressure grouting pipe 4 is connected to the grouting device 6 through the inner cavity of the power head 5. The split drilling tool includes the drill bit split drilling tool 1, Expanding diameter split drilling tool 2 and at least one left-handed split drilling tool 3, such as image 3 As shown, the middle part of the expanded-diameter split drilling tool 2 is an equal-diameter hollow cylindrical extruded body 21, and the top of the extruded body 21 is provided with an upper conical frustum 22 whose outer diameter gradu...
Embodiment 2
[0050] Such as Figure 6 As shown in the figure, a squeeze concrete pile with spraying, expanding holes, and its pile body is composed of a pile body 101, a diameter expanding body 102 and a pile end 103. The pile body is composed of concrete 100, cement soil layer 200 and compacted Soil layer 300. A reinforcement cage 400 is provided in the pile body.
[0051] The diameter expanding body 102 is set in the soil layer with higher deformation modulus and high shear resistance.
[0052] The maximum diameter of the pile body 101 is smaller than the maximum diameter of the expanding body 102 , and the maximum diameter of the pile body 101 is greater than or equal to the maximum diameter of the pile end 103 .
[0053] The expanding body 102 is a truncated double-conical expanding body integrally formed with the pile body 101, and the number thereof is one. The angle α between the lower slope of the double-cone frustum expanding body and the central axis of the pile body is α=5°~8...