Integrally-poured building house construction method
A construction method and housing technology, applied in the direction of construction and building structure, can solve the problems of long construction period, impact on construction efficiency, long construction period of houses, etc., and achieve improved construction quality and efficiency, good technical and economic effects, and high popularization and application. effect of value
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0035] Embodiment 1 A kind of building construction method of integrated pouring
[0036] An integrated pouring building construction method, comprising the following steps:
[0037] (1) Preparation before construction:
[0038] Build pile foundations: according to the construction drawings, build building pile foundations on the construction base;
[0039] Foundation treatment: After the pile foundation is lapped, the floating soil in the site and the mud left during the pile foundation construction should be cleaned up, leveled with an excavator, and compacted with a road roller; finally, a road is opened on both sides of the foundation. Drainage ditch to ensure smooth drainage and avoid rainwater soaking the foundation;
[0040] Foundation construction: On the treated foundation, build a building model according to the construction drawings;
[0041] Material preparation: prepare concrete according to the following parts by weight:
[0042] 180 parts of cement, 45 parts...
Embodiment 2
[0055] Embodiment 2 A kind of building construction method of integrated pouring
[0056] An integrated pouring building construction method, comprising the following steps:
[0057] (1) Preparation before construction:
[0058] Build pile foundations: according to the construction drawings, build building pile foundations on the construction base;
[0059] Foundation treatment: After the pile foundation is lapped, the floating soil in the site and the mud left during the pile foundation construction should be cleaned up, leveled with an excavator, and compacted with a road roller; finally, a road is opened on both sides of the foundation. Drainage ditch to ensure smooth drainage and avoid rainwater soaking the foundation;
[0060] Foundation construction: On the treated foundation, build a building model according to the construction drawings;
[0061] Material preparation: prepare concrete according to the following parts by weight:
[0062] 190 parts of cement, 50 parts...
Embodiment 3
[0075] Embodiment 3 A kind of building construction method of integrated pouring
[0076] An integrated pouring building construction method, comprising the following steps:
[0077] (1) Preparation before construction:
[0078] Build pile foundations: according to the construction drawings, build building pile foundations on the construction base;
[0079] Foundation treatment: After the pile foundation is lapped, the floating soil in the site and the mud left during the pile foundation construction should be cleaned up, leveled with an excavator, and compacted with a road roller; finally, a road is opened on both sides of the foundation. Drainage ditch to ensure smooth drainage and avoid rainwater soaking the foundation;
[0080] Foundation construction: On the treated foundation, build a building model according to the construction drawings;
[0081] Material preparation: prepare concrete according to the following parts by weight:
[0082] 200 parts of cement, 55 parts...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com