A technology of rock slope and control method, which is applied in the direction of excavation, sheet pile wall, construction, etc., can solve the problems of increased additional stress of anchor cables, uncoordinated support, failure of anchor cables, etc., so as to reduce construction difficulty and prevent The effect of anchor cable failure and small transmission loss
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0031] The present invention will be further described below in combination with specific embodiments, so that those skilled in the art can better understand the present invention and implement it, but the examples given are not intended to limit the present invention.
[0032] like Figures 1 to 6 As shown, a method for precise control of the hole-forming line shape of the anchor cable on the high and steep rock slope with fractures, including the following steps:
[0033] a. Locate the position of the anchor cable hole 6, and determine the inclination angle and diameter of the anchor cable hole 6. With the anchor cable hole 6 as the center, arrange three reinforcement holes 7 tangent to the outer diameter of the anchor cable hole 6, three The connecting line between the center points of the reinforcement hole 7 is an equilateral triangle, and the diameter of the reinforcement hole 7 is determined;
[0034] b. Construction of reinforcement hole 7:
[0035] Fix the angle fix...