Load adjustable time potential measuring and calculating method and system for steel technological process
A technology for process flow and steel, applied in the field of load-adjustable time potential measurement, which can solve the problems of complexity, nonlinear production scheduling, and difficulty in estimating the load-adjustable potential of steel process flow
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0056] The present invention provides a method and system for measuring and calculating the load adjustable time potential for iron and steel technological processes, such as figure 1 shown, including:
[0057] Step 1: Obtain each activity and the processing time of each activity in the production process of the iron and steel industry;
[0058] Step 2: Determine the earliest occurrence time and latest occurrence time of each activity based on the activities and the processing time of each activity and the pre-built steel industry production process model;
[0059] Step 3: Determine the adjustable potential time of each activity based on the earliest occurrence time and latest occurrence time of each activity;
[0060] Wherein, the production process model of the iron and steel industry utilizes the top-down hierarchical extension method of Petri nets to establish the production process of the iron and steel industry.
[0061] Among them, S1 is divided into two parts, specif...
Embodiment 2
[0103] In order to prove the effectiveness and accuracy of the proposed method, as well as the accuracy of the model built in this paper, the following cases are selected for simulation verification in this paper, in which the AOE network modeling of the key process of the production process is as follows: Figure 5 shown.
[0104] Calculate the earliest start time and latest start time of the AOE network according to the MATLAB simulation software programming as shown in the following table:
[0105] Table 1 The earliest and latest start schedule of AOE network
[0106]
[0107] Then, according to the earliest and latest start schedule of the AOE network, draw the key process identification map of the production process, such as Figure 6 Shown: Among them, V0, V1, V4, V6, and V8 processes are critical paths, and the processes between the processes do not have the potential for time adjustment. Other process activities such as a1 have a time adjustable potential of 2, and...
Embodiment 3
[0110] Based on the same inventive idea, the present invention also provides a load-adjustable time potential measurement system for iron and steel technological processes, such as Figure 7 Shown: includes:
[0111] The acquisition module is used to acquire each activity and the processing time of each activity in the production process of the iron and steel industry;
[0112] A time determination module, configured to determine the earliest occurrence time and the latest occurrence time of each activity based on the activities and the processing duration of each activity and the pre-built steel industry production process model;
[0113] A potential calculation module, configured to determine the adjustable potential time of each activity based on the earliest occurrence time and the latest occurrence time of each activity;
[0114] Wherein, the production process model of the iron and steel industry utilizes the top-down hierarchical extension method of Petri nets to estab...