On-site construction method for sandwich composite wall

A composite wall, on-site construction technology, applied in the direction of walls, building components, buildings, etc., can solve the problems of peeling off the outer wall, difficult to repair the wall, peeling off the surface of the outer wall, etc., to improve the thermal insulation effect, the construction And the effect of improving efficiency and improving construction safety

Inactive Publication Date: 2014-09-24
山东万斯达建筑工业化研究院有限公司
View PDF7 Cites 3 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Install the prepared insulation layer on the inner side of the prefabricated outer wall, and then pour concrete on the inner side of the insulation layer to form an inner wall after curing. After curing, remove the formwork and the wall-through screw to form a sandwich composite wall. The disadvantages of this construction are: It is necessary to fill all the through holes left on the outer wall and the insulation layer. Since there are many through holes on the wall, it takes more man-hours to complete the hole filling, and it needs to be waterproofed. At the same time, it takes more time to fill the holes. High technology and sense of responsibility often cause water to enter the wall due to improper handling. This is also one of the reasons for water seepage in the interior walls of many building walls. This kind of wall is extremely difficult to repair, especially when frost swelling occurs in winter. cracks and other phenomena are prone to occur, and in severe cases, the surface of the outer wall will fall off
The thermal insulation effect of the insulation layer is greatly reduced; there are many materials for setting up scaffolding, the operation of disassembling and assembling scaffolding is complicated, and the risk factor of working at heights outside the wall is high
At the same time, due to the poor structure of the connecting parts, cracks are prone to appear on the surface of the outer wall, and in severe cases, the outer wall skin will fall off.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • On-site construction method for sandwich composite wall
  • On-site construction method for sandwich composite wall
  • On-site construction method for sandwich composite wall

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0012] A kind of on-site construction method of a sandwich composite wall according to the present invention comprises the following steps: 1. making a concrete outer wall 1 on a factory production line, compounding an insulating layer 2 on the outer wall 1, and forming an insulating layer on the outer wall 1 and the insulating layer 2, the first casing 27 is pre-embedded, one end of the first casing 27 is located on the outer end surface of the insulation layer 2, the other end of the first casing 27 is located in the middle of the outer wall 1, and an internal thread is arranged in the first casing 27. A non-metallic connecting rod 6 penetrates the insulation layer 2, so that the first anchor 12 on the connecting rod 6 is inserted into the outer wall body 1, and the annular baffle plate 9 on the connecting rod 6 is located at the outer edge of the right end of the insulation layer 2 , the ring-shaped sealing platform 11 on the connecting rod 6 is located in the insulation lay...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention provides an on-site construction method for a sandwich composite wall. The on-site construction method for the sandwich composite wall comprises the following steps: (1) manufacturing a concrete external wall on an industrialized production line; compounding an insulating layer on the external wall; embedding a first casing pipe in the external wall body and the insulating layer; enabling a non-metallic connecting rod to penetrate the insulating layer, enabling a first anchoring body on the connecting rod to be placed in the external wall, and enabling a second anchoring body on the connecting rod to be located at the outer side of the insulating layer to form a two-layer composite wall; (2) transporting the two-layer composite wall to a construction site; arranging a template at the outer side of the insulating layer in the two-layer composite wall, and arranging a second casing pipe between the port of the first casing pipe and the template to form a cavity between the insulating layer and the template; (3) pouring concrete in the cavity for maintenance to form an internal wall; (4) removing a threaded rod and the template, and then, filling and leveling up the cavities of the casing pipes with the concrete to form the sandwich composite wall after the maintenance. According to the on-site construction method provided by the invention, compounding of the external wall and the insulating layer is finished during industrialized production, and pouring of the internal wall is finished at the construction site, so that the defects of the prior art are solved.

Description

technical field [0001] The invention relates to building walls, and relates to a field construction method for sandwich composite walls. Background technique [0002] At present, the sandwich composite building wall includes three layers, an outer wall, an insulation layer and an inner wall. The construction method is as follows: prefabricate the concrete outer wall, leave through holes during prefabrication, and pre-embed casings to install wall-through screw rods. The outer wall can act as an outer formwork during construction. During construction, scaffolding is set on the outside of the wall, and a support formwork is set on the inside of the wall. Screws are used to pass through the casing and formwork, and tightening is used on both sides of the wall. Firmware is tight. Install the prepared insulation layer on the inner side of the prefabricated outer wall, and then pour concrete on the inner side of the insulation layer to form an inner wall after curing. After curi...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E04B2/00E04G21/00
Inventor 张立琦张波张树辉朱天翼
Owner 山东万斯达建筑工业化研究院有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products