Complete flow unit productivity allocation control method for metallurgical enterprise

A control method and technology of the whole process, applied in the direction of program control, comprehensive factory control, comprehensive factory control, etc., can solve the problems such as the inability to take into account the processing needs of multiple units at the same time, the inability to adapt to the continuous operation mode of the unit, and the inability to dynamically consider the processing status.

Active Publication Date: 2015-05-20
NORTHEASTERN UNIV
View PDF5 Cites 13 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Due to the dynamic change of unit status, there are many processing constraints in each process, and there are various types of materials to be considered, and the quantity is huge. Manually formulating a unit capacity allocation control plan cannot take into account the processing needs of multiple units at the same time; at the same time, this method is due to the lack of real-time It is impossible to dynamically consider the processing status of each unit, and formulate a unit capacity allocation control plan to ensure stable operation of the unit and qualified product quality; in addition, the execution response time of manually prepared reports is long, and the units of large metallurgical enterprises are mostly in continuous operation. This manual method cannot adapt to the continuous operation mode of the unit

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Complete flow unit productivity allocation control method for metallurgical enterprise
  • Complete flow unit productivity allocation control method for metallurgical enterprise
  • Complete flow unit productivity allocation control method for metallurgical enterprise

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0061] The specific implementation manners of the present invention will be described in detail below in conjunction with the accompanying drawings.

[0062] The production capacity distribution control method of the whole process of metallurgical enterprises in this implementation mode adopts the production capacity distribution control system of the whole process of metallurgical enterprises, and its structure is as follows figure 2 As shown, the configuration is as follows: a server, a cable connection and a router; wherein, the server is used to realize the production capacity distribution control method of the whole process of metallurgical enterprises in metallurgical enterprises of the present invention, and communication equipment such as routers and cable interfaces are used to realize communication with the enterprise. The communication connection between the automatic control systems of the production sites of each unit achieves the purpose of optimizing the product...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention provides a complete flow unit productivity allocation control method for a metallurgical enterprise. The complete flow unit productivity allocation control method comprises the steps that a complete flow unit productivity allocation control model of the metallurgical enterprise is established according to the production state of each unit and the contractual processing route of the metallurgical enterprise; the productivity allocation situation of each unit is determined, including the contract selection situation and the contract processing sequence of each unit, and the stability estimation index value of the complete flow unit productivity allocation control scheme of the metallurgical enterprise is calculated; the productivity distribution control is carried out according to the complete flow unit productivity allocation control scheme of the metallurgical enterprise and the corresponding production contract , and the complete flow unit productivity allocation control scheme of the metallurgical enterprise is adjusted in real time; the complete flow unit optimal productivity allocation control scheme of the metallurgical enterprise is issued to the complete flow unit for productivity distribution control. According to the complete flow unit productivity allocation control method for the metallurgical enterprise, the productivity allocation scheme is established by coordinating the units, so that the requirements of production equipment are met to the greatest extent, the production of each unit can be carried out stably, the production process is more reasonable, and the production switching is reduced.

Description

technical field [0001] The invention belongs to the technical field of metal material processing information, and specifically relates to a method for controlling the production capacity distribution of a full-process unit in a metallurgical enterprise. Background technique [0002] The unit load distribution problem in the process of metal material processing is the main content of the production management of metallurgical enterprises. The quality of capacity distribution is directly related to the equipment stability and operating efficiency of each unit in the production plant, product quality and production cost. [0003] Take steel mills as an example: large-scale iron and steel enterprises often cover multiple serial processing procedures including ironmaking, steelmaking, hot rolling, cold rolling, etc. Ironmaking uses iron ore powder and coke as the main raw materials, and after a series of smelting processes the final Forming molten iron; steelmaking is a smelting ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): G05B19/418
CPCY02P90/02G05B19/41865
Inventor 唐立新杨阳
Owner NORTHEASTERN UNIV
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products