A prefabricated assembly structure of superimposed integral comprehensive pipe gallery and its construction method

A technology of prefabricated assembly and comprehensive pipe gallery, which is applied in the direction of basic structure engineering, underwater structures, artificial islands, etc., can solve the problems that the stress safety between nodes cannot be guaranteed, and the joints of prefabricated components are prone to water seepage and leakage, etc., to achieve Strengthen the strength and rigidity, save the construction period and cost, and ensure the effect of effective connection

Active Publication Date: 2018-11-23
CHINA STATE CONSTRUCTION ENGINEERING CORPORATION +1
View PDF6 Cites 1 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0007] The purpose of the present invention is to provide a prefabricated assembly structure of a superimposed integrated comprehensive pipe gallery and its construction method. To solve the prefabricated assembly of existing underground projects, the safety of stress cannot be guaranteed between nodes, and the joints between prefabricated components are prone to water seepage Technical problems with water leaks

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A prefabricated assembly structure of superimposed integral comprehensive pipe gallery and its construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0046] Examples see figure 1 As shown, a prefabricated assembly structure of a superimposed integral integrated pipe gallery is the construction of the main structure of a single-layer double-span integrated pipe gallery.

[0047] The prefabricated assembly structure includes an enclosure structure located in the foundation pit 1, a pipe gallery prefabricated assembly structure arranged between the enclosure structure 1, a floor cushion 2 under the pipe gallery prefabricated assembly structure, and the outer surface of the pipe gallery prefabricated assembly structure. The fully outer waterproof layer 11 of the pipe gallery is filled with backfilling soil 10 above the prefabricated assembly structure of the pipe gallery, and the floor cushion 2 is laid horizontally along the lower side of the prefabricated assembly structure of the pipe gallery;

[0048] The prefabricated assembly structure of the pipe gallery is composed of a cast-in-place bottom plate 3 at the bottom, stacked sid...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses an overlapping integral type prefabricated assembly structure for a comprehensive pipe gallery and a construction method thereof. The overlapping integral type prefabricated assembly structure comprises envelop enclosures, a pipe gallery prefabricated assembly structure body, a bottom plate cushion course and a completely outer-cladding waterproof layer, wherein the envelop enclosures are located in a foundation pit; the pipe gallery prefabricated assembly structure body is arranged between the envelop enclosures; the bottom plate cushion course is arranged under the pipe gallery prefabricated assembly structure body; and the completely outer-cladding waterproof layer is arranged on the outer side surface of the pipe gallery prefabricated assembly structure body in a cladding mode. The upper portion of the pipe gallery prefabricated assembly structure body is filled with backfill earth, and the completely outer-cladding waterproof layer is arranged on the outer side surface of an outer side cast-in-situ part of the pipe gallery prefabricated assembly structure body in a cladding mode. The construction method of the overlapping integral type prefabricated assembly structure comprises the steps of prefabricated component machining, foundation pit excavation, bottom plate pouring, side wall construction, mid-partition construction, top plate construction, earth backfilling and the like. According to the overlapping integral type prefabricated assembly structure for the comprehensive pipe gallery and the construction method thereof, the prominent problems of force bearing of joints, water seepage of connection seams and the like in the underground engineering prefabrication process are solved; and the structural modes of bottom plate casting in situ, side wall single-layer overlapping, mid-partition double-layer overlapping, top plate overlapping, all-joint casting in situ and completely outer-side waterproof layer cladding are adopted, so that effective connection and the waterproof function of the joints are ensured.

Description

Technical field [0001] The invention relates to a prefabricated assembly structure and a construction method thereof, in particular to a laminated integral assembly structure of a comprehensive pipe gallery and a construction method thereof. Background technique [0002] With the rapid development of the economy and the continuous improvement of the level of urbanization, the development of underground space is also increasing. In recent years, comprehensive underground pipe corridors have become the direction of domestic vigorous development. At present, due to construction conditions and waterproof requirements, the main structure of integrated underground pipe gallery is most commonly cast-in-place concrete structure. [0003] However, since the cast-in-situ underground structure is poured on-site artificially, the following defects and ills are inevitable: [0004] 1. It takes time to bind the steel cage and support the concrete formwork. The internal construction of the main st...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E02D29/045
CPCE02D29/10
Inventor 郭建涛油新华耿冬青许国光马庆松
Owner CHINA STATE CONSTRUCTION ENGINEERING CORPORATION