A pouring system and design method technology, applied in casting molding equipment, metal processing equipment, casting molds, etc., can solve problems such as difficult to ensure smooth filling of molten metal, unreasonable pouring system, etc., to achieve stable pouring speed and prevent erosion Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0055] A certain type of machine tool bed is poured, the pouring material is HT250, the pouring temperature is 1360°C, and the weight of the casting is 10t. The size of the cross-sectional area is Φ55mm, and the height of sprue 1 is 1650mm. The design principle is the principle of equal flow rate. The design of the upper part and the lower part is conducive to the floating of gas and inclusions to the top, and at the same time, it can avoid the erosion of the molten metal on the sprue.
[0056] As shown in Figure 3, Figure 5 As shown, the corner of the sprue 1 and the first row of runners 3-1 adopts an arc bend 2 for transition, the radius of the arc bend 2 is 80mm, and the equivalent diameter of the first row of runners 3-1 is 60mm , The cross-sectional area of the arc bend 2 is designed to be variable in diameter, and the diameter changes between 55 mm to 90 mm to avoid negative pressure at the corner and cause entrainment. It can be seen that the present invention is dif...
Embodiment 2
[0061] A certain type of machine tool bed is poured, the pouring material is HT250, the pouring temperature is 1370°C, and the weight of the casting is 5t. The size is Φ50mm, and the height of the sprue 1 is 1000mm. The design principle is the principle of equal flow rate. The design of the upper part and the lower part is conducive to the gas and inclusions floating to the top, and at the same time, it can avoid the erosion of the molten metal on the sprue 1.
[0062] As shown in Figure 2, Image 6 As shown, the corner of the sprue 1 and the first row of runners 3-1 adopts an arc bend 2 for transition, the radius of the arc bend 2 is 80mm, and the equivalent diameter of the first row of runners 3-1 is 60mm , The cross-sectional area of the arc bend 2 is designed to be variable in diameter, and the diameter changes between 55 mm to 90 mm to avoid negative pressure at the corner and cause entrainment. It can be seen that the present invention is different from the prior art. ...