Open steel tube concrete structure with batten plates on cold-formed turned edge
A technology of steel pipe concrete and curling band, which is applied in the direction of building structure and construction, can solve the problems of difficulty in ensuring the quality of inner filling concrete, stress concentration at the corners of multilateral steel pipes, and inconvenient fabrication of assembled steel pipes, etc., and it is easy to guarantee the quality , weakening of stiffness and torsional performance, and improvement of fatigue performance and structural rigidity
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0042] Such as figure 1 As shown, the embodiment 1 of the present invention includes a rectangular steel pipe 1 with an outer opening, a trim plate 2 evenly arranged in the direction of the opening of the rectangular steel pipe 1 , an inner filling concrete 3 filled inside the rectangular steel pipe 1 with the opening, and a rectangular steel pipe arranged at the opening according to the design requirements. The PBL stiffener 4 on the inner wall of the steel pipe 1 .
[0043] In the actual production of the open rectangular steel pipe 1, first draw the reference line for cold bending and rolling of the steel plate on the steel plate with the designed thickness according to the designed rectangular steel pipe size, and then weld the PBL stiffener 4 on the steel plate as required, as shown in figure 2 shown. Then in the factory, the steel plate containing the PBL stiffener 4 is rolled into a seamless open rectangular steel pipe 1 according to the order of cold bending and rollin...
Embodiment 2
[0046] Such as Figure 7 As shown, Embodiment 2 of the present invention includes the hexagonal steel pipe 5 with the outer opening, the trim plate 2 evenly arranged in the opening direction of the hexagonal steel pipe 5, the inner filling concrete 3 filled in the inner side of the hexagonal steel pipe 5 and according to The design requires the PBL stiffeners 4 arranged on the inner wall of the open hexagonal steel pipe 5 .
[0047] In the actual production of the open hexagonal steel pipe 5, first draw a reference line for cold bending and rolling of the steel plate on the steel plate with the designed thickness according to the designed hexagonal steel pipe size, and then weld the PBL stiffener 4 on the steel plate as required, such as Figure 8 shown. Then in the factory, the steel plate containing the PBL stiffener 4 is rolled into a seamless open hexagonal steel pipe 5 according to the order of cold bending and rolling, and the order of cold bending and rolling is as fol...