Road repairing construction process for filling-digging junction roadbed section
A technology of road repair and construction technology, applied in the direction of roads, roads, infrastructure engineering, etc., can solve problems such as reducing road safety, subsidence, road surface cracks, etc., achieving a significant reinforcement effect, a small disease recurrence rate, and repairing the road surface. cracking effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0029] Embodiment 1: A kind of road restoration construction technology of subgrade road section at the junction of filling and excavation, comprising the following steps:
[0030] 1) Hole location layout; lay out grouting holes according to the drawings, measure and place the points of anti-slide piles, make marks on the points, and determine the depth of the pile bottom relative to the ground;
[0031] 2) Hole forming: use a drilling machine to drill holes on the surface layer and penetrate the surface layer to the designed depth;
[0032] 3) Clear the hole; blow away the dregs and bad soil in the hole;
[0033] 4) Lower the grouting pipe; after the hole is formed, lower the grouting pipe, and a plurality of Φ6 flower holes are opened at the lower part of the grouting pipe;
[0034] 5) Pile body filling; use gravel as aggregate and mix cement to fill the hole, and fill it to a place 1m below the top surface of the pavement layer;
[0035] 6) prepare slurry; prepare slurry ...
Embodiment 2
[0046] Embodiment 2: A kind of road restoration construction technology of subgrade section at the junction of filling and excavation, comprising the following steps:
[0047] 1) Hole location layout; lay out grouting holes according to the drawings, measure and place the points of anti-slide piles, make marks on the points, and determine the depth of the pile bottom relative to the ground;
[0048] 2) Hole forming: use a drilling machine to drill holes on the surface layer and penetrate the surface layer to the designed depth;
[0049] 3) Clear the hole; blow away the dregs and bad soil in the hole;
[0050] 4) Lower the grouting pipe; after the hole is formed, lower the grouting pipe, and a plurality of Φ6 flower holes are opened at the lower part of the grouting pipe;
[0051] 5) Pile body filling; use gravel as aggregate and mix cement to fill the hole, and fill it to a place 1m below the top surface of the pavement layer;
[0052] 6) prepare slurry; prepare slurry accor...
Embodiment 3
[0065] Embodiment 3: A kind of road restoration construction technology of subgrade road section at the junction of filling and excavation, comprising the following steps:
[0066] 1) Hole layout: lay out grouting holes according to the construction drawing, measure and place the points of the anti-slide piles, mark the points, and determine the depth of the pile bottom relative to the ground;
[0067] 2) Hole forming: use a drilling machine to drill holes on the surface layer and penetrate the surface layer to the designed depth;
[0068] 3) Clear the hole; blow away the dregs and bad soil in the hole;
[0069] 4) Lower the grouting pipe; after the hole is formed, lower the grouting pipe, and a plurality of Φ6 flower holes are opened at the lower part of the grouting pipe;
[0070] 5) Pile body filling; use gravel as aggregate and mix cement to fill the hole, and fill it to a place 1m below the top surface of the pavement layer;
[0071] 6) prepare slurry; prepare slurry ac...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More