Drainage positioning grouting segment and construction method thereof

A technology of grouting pipe and grouting pipe, which is applied in the directions of drainage, earthwork drilling, wellbore lining, etc., can solve the problems of segment deformation, settlement deformation, and many construction links.

Active Publication Date: 2020-12-04
ZHEJIANG UNIV CITY COLLEGE
View PDF7 Cites 4 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, this method has the following disadvantages: 1. The original waterproof layer of the segment is easily damaged during the drilling process, which threatens the durability of the segment and adversely affects the tunnel and the surrounding environment; 2. There are many construction links on site, It is difficult to deal with emergency segment deformation and prone to hole collapse, resulting in segment damage and economic losses; 3. On-site drilling is easily constrained by the environment. If the external water pressure and soil pressure are too large, it will cause engineering problems such as sudden surge and piping; 4. The crack grouting sealing technology cannot deal with all the segment leakage problems; 5. The effect of groundwater pressure on the segment cannot be reduced or eliminated by the crack grouting sealing method; 6. The grouting reinforcement cannot eradicate the settlement and segment deformation, the drilling holes in the prior art cannot be used multiple times, and the cost is relatively high
[0004] Therefore, in order to repair the problems of settlement deformation and segment leakage during the operation of the tunnel, and in view of the current engineering status of the urban underground environment that is increasingly complex and related grouting reinforcement technology is not perfect, there is an urgent need for a new type of construction that is fast, simple, safe and effective. Grouting reinforcement technology

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Drainage positioning grouting segment and construction method thereof
  • Drainage positioning grouting segment and construction method thereof
  • Drainage positioning grouting segment and construction method thereof

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0052] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.

[0053] like Figure 1-14 As shown, a drainage positioning grouting segment provided in this embodiment includes a prefabricated segment body 1 and a grouting drainage system; the prefabricated segment body 1 includes a segment solid body 1-1, and the segment solid body 1-1 is provided with a prefabricated borehole 1-2 and a prefabricated water pressure pore sensor installation hole 1-3; the prefabricated borehole 1-2 is prefabricated during the pouring process of the segment, and there is no need to carry out the prefabrication of the segment during the service stage of the tunnel. On-site construction avoids common engineering problems of traditional on-site segment drilling construction technology; the hole wall is threaded for fixing the sealing device, that is, the air bag 4 .

[0054] The grouting drainage system includes a pre-installed valve 2 ,...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a drainage positioning grouting segment and a construction method thereof. The drainage positioning grouting segment comprises a prefabricated segment body and a grouting drainage system, wherein the prefabricated segment body comprises a segment solid body, a prefabricated drill hole and a preset water pressure pore sensor mounting hole; the grouting drainage system comprises a pre-installed valve, a pre-embedded air bag, a grouting drainage guide pipe and a water pressure pore sensor; and when the water pressure collected by the water pressure pore sensor exceeds a segment stress early warning value, the engineering problems such as segment deformation and crack water seepage can be prevented by opening the valve for drainage or by opening the valve for drainage first and then conducting grouting reinforcement. According to the drainage positioning grouting segment and the construction method thereof, the prefabricated drill hole and the pre-embedded groutingdrainage system are adopted, on-site drilling and grouting drainage device mounting on a shield segment are not needed, drainage is conducted directly through the pre-installed valve, grouting is conducted through the pre-embedded grouting drainage guide pipe after the valve is dismounted, prevention and rapid and safe treatment of common engineering problems of the shield segment are achieved, the construction cost is reduced, and the construction period is shortened.

Description

technical field [0001] The invention relates to the technical field of prefabricated segment production in underground shield subway tunnel engineering, in particular to a drainage positioning grouting segment and a construction method thereof. Background technique [0002] In recent years, the construction of subway tunnels in many cities in my country has entered a stage of great development. Statistics show that as of December 31, 2019, a total of 40 cities in mainland my country have opened urban rail transit operating lines, with an operating mileage of 6,730.27 kilometers, and still maintain a rapid growth trend. In 2019, only 968.77 kilometers of new operating lines in mainland China , including 891.83 kilometers of subway. With the large increase of close construction and the continuous disturbance of vibration to the soil around the tunnel during the operation of the subway, the surrounding environment of the tunnel has changed, resulting in deformation and damage o...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E21D11/00E21D11/08E21D11/10E21D11/38E21B33/126E21F16/02
CPCE21D11/003E21D11/08E21D11/086E21D11/105E21D11/38E21B33/126E21B33/1208E21F16/02
Inventor 章丽莎叶佳欢魏纲李炯韬孙逸夫崔允亮孙苗苗
Owner ZHEJIANG UNIV CITY COLLEGE
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products