A technology for positioning tooling and steel pipe piles, applied in sheet pile walls, infrastructure engineering, construction, etc., can solve the problems of strength, adverse effects of installation orientation, long idle time of machinery, and impact of steel pipe piles, so as to avoid mechanical idleness. , The effect of good installation quality and low construction cost
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0033] like figure 1 In the shown embodiment, a steel pipe group pile vibration piling method, in this embodiment, take the three-pipe tower as an example, the three-pipe tower foundation
[0034] The foundation includes three steel pipe piles 1, and the span between the steel pipe piles is 2980mm. The diameter of the steel pipe piles is 600mm, and the length is 8m. Before construction, fully prepare man-machine materials, including the following steps:
[0035] S1: Foundation survey, find out the topography and hydrology of the site and the interference with the artificial geological conditions of the steel pipe group piles, analyze the geological conditions of the site, and the survey is as follows:
[0036] For pile positions in rock layers, gravel layers, and gravel layers, replace the pile positions of the steel pipe group piles or perform foundation pretreatment on the site; foundation pretreatment includes: using a drilling rig to drill several holes in the pile positio...