A technology of pole and tower foundation and construction method, applied in the direction of foundation structure engineering, foundation structure test, sheet pile wall, etc., can solve the problems of unsatisfactory bearing capacity, unsatisfactory effect, unsafe hidden danger, etc. , Good technical support, convenient construction effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0063] The present invention provides an embodiment, which is a construction method of micro-piles for pole and tower foundations in soft soil foundations. The micro-piles described in the present invention, namely MP piles, are developed on the basis of existing tree root piles. A new type of pile foundation. The difference between MP piles and traditional tree root piles is that the secondary grouting process is used. Therefore, the MP pile is a pile body with variable cross-section. Through the secondary grouting process, the bearing capacity of the single pile in the soft soil foundation can be greatly improved.
[0064] A kind of construction method of pole tower foundation miniature pile in the soft soil foundation of the present invention, specifically comprises the following steps:
[0065] Step 1. Bind the reinforcement cage 3 and the secondary grouting pipe 2.
[0066] During construction, first bind the 1-inch secondary grouting pipe 2 on the reinforcement cage 3 ...
Embodiment 2
[0167] The present invention provides another embodiment, which is a construction method of miniature piles in a soft soil foundation, such as the construction method described in embodiment 1. When constructing, all the test piles are 15m long and the pile diameter is 250mm. Except for D-7 and D-8 test piles, φ219×4mm steel pipes are used instead of steel cages within 3m of the pile tops of other test piles, and the reinforcement of the pile body is 8φ14 in the 3-10m part, and the reinforcement in 10-15m is halved; The stirrup adopts spiral stirrup φ6@200, and a φ12 welded stiffening stirrup is installed every 2m, and the pile top stirrup is strengthened. Figure 4-2 . The cement uses No. 425 ordinary Portland cement, and the crushed stone aggregate 6 uses washed crushed stone with a particle size of 15-25mm. The water-cement ratio of primary grouting is 0.5, and the water-cement ratio of secondary grouting is 0.5. The size of the single pile cap is 0.6×0.6×0.5 (height) m, ...