Sludge treatment method and treatment system for brine storage pool
A technology of sludge treatment and treatment method, which is applied in the field of sludge treatment method and treatment system in brine storage tanks, can solve the problems of high investment cost, parking and operation, etc., and achieve the effect of economic benefit and high reuse rate
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0028] The present embodiment provides a method for treating sludge in a brine storage tank, comprising the following steps:
[0029] Step 1: Disconnect the waste water pipeline from the first water pump 3 of the first regeneration waste water storage tank 4 to the fresh water tank 2, and connect the disconnected waste water pipeline nozzle and the mud pump 18 of the brine storage tank 1 through the first pipeline 10 to connect. Preferably, when disconnecting the waste water pipeline from the first regenerated waste water storage tank 4 into the fresh water tank, lead the disconnected waste water pipeline mouth to the ground, and then connect the mud pump 18 to the disconnected waste water pipeline through the first pipeline 10 Connect the nozzle. Preferably, the first pipeline 10 may be a temporary rubber tube.
[0030] Step 2: Disconnect the waste water pipeline from the first water pump 3 of the first regeneration waste water storage tank 4 to the primary brine purificati...
Embodiment 2
[0038] like figure 1As shown, this embodiment provides a sludge treatment system for a brine storage tank, including a brine storage tank 1 , a first regenerated wastewater storage tank 4 and a primary brine slag tank 12 . The brine storage tank 1 is provided with a mud pump 18, and the outlet of the mud pump 18 is connected to the waste water pipeline nozzle disconnected from the first water pump 3 of the first regenerated waste water storage tank 4 to the fresh water tank 2 through the first pipeline 10. The first water pump 3 of the first regeneration wastewater storage tank 4 is connected to the first brine slag pool 12 through the second pipeline 11 to the waste water pipeline nozzle disconnected in the primary refined brine process; 10 and the second pipeline 11 to the brine storage tank sludge extraction pipeline of the primary brine slag tank 12 . Preferably, a plate-and-frame filter press or a centrifuge is provided in the primary brine slag pool. During processing, ...
Embodiment 3
[0044] This embodiment is described by taking a chlor-alkali enterprise as an example.
[0045] A chlor-alkali enterprise currently has four groups of nine salt wells connected horizontally, with a daily output of brine of 350m3. The first- and second-line caustic soda plants have two brine storage tanks with a diameter of 50m and a volume of 10793m 3 , mainly plays the role of storing brine and buffering production. Since the brine storage tank was completed and put into operation in 2004, it has not been dredged. However, with the extension of the operation time, the sediment entrained by the return brine continued to deposit, and the effective volume of the brine tank continued to decrease. Until 2018, the 2# brine The effective volume of the pond has dropped to 33%. In order to increase the effective volume of the brine pond, in April 2018, the company used excavators to clear about 1000m of sludge from the 2# brine pond. 3 However, the excavated salt mud is thin and dif...