Construction method drive type major diameter steel pipe pore-creating filling pile

A construction method and cast-in-situ pile technology, which can be applied to sheet pile walls, foundation structure engineering, construction, etc., can solve the problems of mechanical hole depth limitation, low operation safety, and non-environmental protection, so as to save engineering cost and ensure safe and reliable structure , the effect of short construction period

Inactive Publication Date: 2008-12-17
DALIAN GREAT GOLDEN HORSE INFRASTRUCTURE
View PDF0 Cites 2 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] The traditional construction methods of cast-in-place piles mainly include artificial hole-dug cast-in-place piles and mechanical hole-forming mud wall-protected cast-in-place piles. These two methods mainly have several deficiencies: during the hole-forming process of manual-dug hole-dug cast-in-situ piles, construction personnel are safe to operate. Low performance, the problem of hole collapse that often occurs in the process of mechanical hole forming, the problem of broken piles caused by the permeation of the conduit during the pouring process of the mechanical hole forming underwater conduit, the construction period is long: it takes 10-20 days to manually dig a hole with the same diameter and depth, and the imp

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method drive type major diameter steel pipe pore-creating filling pile
  • Construction method drive type major diameter steel pipe pore-creating filling pile

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0027] The construction method of the driven-in large-diameter steel pipe hole-forming pile,

[0028] The first step is to form a hole: use a large steel pipe with an outer diameter of 2000mm without a steel tip to form a hole, and use a crawler-type diesel pile driver equipped with a guide rod piling hammer and a barrel-type piling hammer to hammer the large steel pipe;

[0029] The second step is to install the reinforcement cage: after taking out the soil in the large steel, install the reinforcement cage in the above-mentioned large steel pipe;

[0030] The third step of pouring: After the installation is completed, concrete is poured into the hole of the reinforcement cage and vibrated. As the concrete is poured and compacted, a hydraulic extubation device is used to extubate. It consists of a hydraulic system and an extubator. The hydraulic system is shown in Figure 2. , the hydraulic oil tank 2 is fixed on the support 1, the oil outlet of the hydraulic oil tank has an o...

Embodiment 2

[0032] Construction method of large-diameter steel pipe perforated pile,

[0033] The first step is to form a hole: use a large steel pipe with a steel pipe outer diameter of 800mm and a prefabricated concrete conical pile tip to form a hole, and use an electro-hydraulic pile driver equipped with a guide rod piling hammer and a barrel piling hammer to hammer the large steel pipe;

[0034] The second step is to install the reinforcement cage: install the reinforcement cage directly in the above-mentioned large steel pipe;

[0035] The third step of pouring: After the installation is completed, concrete is poured into the hole of the reinforcement cage and vibrated. As the concrete is poured and compacted, the hydraulic pipe removal device is used to remove the pipe. The hydraulic pipe removal device is composed of a hydraulic system and a pipe puller. The hydraulic system The arm of the hydraulic cylinder is equipped with an extubation stand, which has an assembly hole, and is ...

Embodiment 3

[0037] Construction method of large-diameter steel pipe perforated pile,

[0038] The first step is to form a hole: use a large steel pipe with an outer diameter of 1000mm and a prefabricated reinforced concrete conical pile tip to form a hole, and use an electro-hydraulic pile driver equipped with a guide rod piling hammer and a barrel piling hammer to hammer the large steel pipe;

[0039] The second step is to install the reinforcement cage: install the reinforcement cage directly in the above-mentioned large steel pipe;

[0040] The third step of pouring: After the installation is completed, concrete is poured into the hole of the reinforcement cage and vibrated. As the concrete is poured and compacted, a hydraulic oil cylinder is used to pull out the large steel pipe that forms the hole and form a pile. The diameter of the pile can reach 1000mm.

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

PropertyMeasurementUnit
Outer diameteraaaaaaaaaa
Diameteraaaaaaaaaa
Diameteraaaaaaaaaa
Login to view more

Abstract

The invention relates to the field of building construction, in particular to a construction method used for punching-typed large-diameter steel pipe hole-forming pouring piles, comprising the steps as follows: step 1: hole forming: the large steel pipe with the external diameter of 800-2000mm is adopted for hole-forming; step 2: reinforced cages-arranging: the reinforced cages are arranged inside the large steel pipes; step 3: pouring: concrete is poured into the hole of the reinforced cage after the installation is complete, simultaneously, the hole-forming large steel pipe is pulled out and the pile is formed. The pouring pipe construction method of the invention can replace the construction of manpower excavating pile and the mechanical hole-forming slurry wall-protection pouring pipe with large diameter, and has the obvious advantages of safe structure, greatly improving the bearing capability of single pile, environmental protection in-situ, safe construction, reducing the construction links and saving the engineering cost, etc., compared with the traditional mechanical boring pouring and manpower excavation pouring pipes.

Description

1. Technical field: [0001] The invention relates to the construction field, in particular to a construction method of cast-in-place piles. 2. Background technology: [0002] The traditional construction methods of cast-in-place piles mainly include artificial hole-dug cast-in-place piles and mechanical hole-forming mud wall-protected cast-in-place piles. These two methods mainly have several deficiencies: during the hole-forming process of manual-dug hole-dug cast-in-situ piles, construction personnel are safe to operate. Low performance, the problem of hole collapse that often occurs in the process of mechanical hole forming, the problem of broken piles caused by the permeation of the conduit during the pouring process of the mechanical hole forming underwater conduit, the construction period is long: it takes 10-20 days to manually dig a hole with the same diameter and depth, and the impact It takes 2-5 days to drill a hole, and 2-3 days for rotary mechanical drilling. En...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): E02D5/38E02D5/72E02D7/06E02D9/00
Inventor 徐世大
Owner DALIAN GREAT GOLDEN HORSE INFRASTRUCTURE
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products