A production process and technology for plastic pipe fittings, applied in the field of outer galvanized inner plastic coated pipe fittings and their production processes, can solve the problems of easy peeling of the coating and poor adhesion, and achieve product quality assurance, high production efficiency, adhesion and impact. and other stable performance
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0015] An outer galvanized inner plastic-coated pipe fitting comprises an outer galvanized layer 1, a malleable steel part base 2, and an inner layer of polyethylene or epoxy / polyester coating 3.
[0016] The specific production process of the outer galvanized inner plastic-coated pipe fittings is as follows:
[0017] A Sand blasting on the inner wall: sand blast the inner wall of the pipe fittings with a sand blasting machine to remove the galvanized layer. Note that the outer galvanized layer must not be damaged.
[0018] B Neutral degreasing and decontamination: ① The ratio of slotting chemical solution is 12%. Fill the tank with water until it is 80% full, and add it slowly while stirring. It can be added flexibly according to the degreasing effect and the degree of oil pollution. ② . Processing time was 7 minutes. Clean up the oil on the liquid surface in time. When the tank liquid is seriously dirty and the effect of adding liquid medicine is not obvious, it shou...