Artificial ecological lake construction method for karst landform
A technology of artificial ecology and construction methods, applied in chemical instruments and methods, marine engineering, water conservancy projects, etc., can solve the problems of long construction period and easy pollution of lake water, and achieve the effect of stable ecological environment and good anti-seepage performance.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0038] A method for constructing an artificial ecological lake for karst landforms, comprising the following steps in sequence:
[0039] S1. Clean up the area where the artificial lake is built, and level the soil at the bottom of the lake;
[0040] S2. Improve the ecological environment of the lake bottom soil;
[0041] S3, injecting water into the area where the artificial lake is built;
[0042] S4. Construct the biome in the lake.
[0043] Further, the method for leveling the soil at the bottom of the lake in the step S1 includes the following steps:
[0044] S101. After excavating the lake base earthwork to the designed lake bottom elevation, continue to dig 0.5-0.7m;
[0045] S102, leveling and compacting the base soil excavated in step S101, backfilling with 0.25-0.35m of clay, and compacting with mechanical rolling;
[0046] S103, paving waterproof material on the clay backfilled in step S102;
[0047] S104. After the waterproof material is laid, backfill the wate...
Embodiment 2
[0065] The method for improving the lake bottom soil ecological environment in the step S2 comprises the following steps:
[0066] S201. Disinfect the bottom mud to eliminate the benthic harmful biological flora;
[0067] S202. After the bottom mud is not disinfected in S201, the bottom mud is activated to build beneficial microbial flora necessary for the ecosystem.
[0068] In the water ecosystem construction project, the first thing is to disinfect the bottom mud, to eliminate the benthic harmful biological flora, choose high-quality Chinese herbal medicine non-toxic disinfectant or use dichloride effervescent tablets, and spray evenly on the entire pool bottom with a knapsack sprayer . After the bottom mud is disinfected, the bottom mud activation work is carried out to build the beneficial microbial flora necessary for the ecosystem, and at the same time increase the activity of the bottom mud, which can improve the survival rate of aquatic plants.
Embodiment 3
[0070] The difference between this embodiment and Embodiment 1 is that the step S401, the method of planting aquatic plants at the bottom of the lake includes:
[0071] A. Preparation before planting
[0072] Plant selection: Selecting plants that meet the design requirements and are free from pests and diseases is the key to ensuring the quality of the project. For example, the main key plants of this project, such as the evergreen underwater bitter grass, choose the modules that grow vigorously, have no pests and diseases, and have well-developed root systems.
[0073] B. Plant Qualitative and Positioning
[0074] The main plant shall be constructed according to the drawings, and if the adjustment is caused by special reasons, it shall be subject to the approval of the designer or the technical change order. Because the planting work is carried out underwater, the water body is easy to cause planting deviation due to turbidity. The construction adopts the method of marking...
PUM
Property | Measurement | Unit |
---|---|---|
Softening point | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com