A method for plugging abandoned wells
A technology for well cleaning and tubing, which is applied in earthwork drilling, sealing/isolation, wellbore/well components, etc. It can solve problems such as hidden dangers left by safe operation of gas storage, natural gas leakage, etc., so as to improve the plugging effect, The effect of ensuring safe operation and avoiding leakage
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0041] This embodiment provides a method for plugging an abandoned well, the plugging method comprising: lowering the oil pipe into the abandoned well 8m above the cement plug.
[0042] Flush the well with fresh water circulation for 2 weeks.
[0043] The water of 980 parts by weight, the bentonite of 40 parts by weight, the sodium carbonate of 2 parts by weight, the barite powder of 1000 parts by weight were mixed, and stirred for 25min, after the bentonite, sodium carbonate and barite powder were mixed with water, they hydrated and swelled, A mixed slurry is formed.
[0044] Add 10 parts by weight of diluent to the mixed slurry and stir for 10 minutes to form a protective plug slurry.
[0045] The protective plug slurry is filled above the cement plug of the abandoned well through the tubing, and the protective plug slurry is left to settle to obtain a protective plug to complete the plugging of the abandoned well.
[0046]The abandoned well plugging method provided in Exa...
Embodiment 2
[0048] This embodiment provides a plugging method for an abandoned well, the plugging method comprising: running an oil pipe into a place 10 m above the cement plug of the abandoned well.
[0049] Flush the well with fresh water circulation for 2 weeks.
[0050] The water of 1000 parts by weight, the bentonite of 50 parts by weight, the sodium carbonate of 2.5 parts by weight, the barite powder of 1025 parts by weight were mixed, and stirred for 30min, after the bentonite, sodium carbonate and barite powder were mixed with water, they hydrated and swelled, A mixed slurry is formed.
[0051] Add 15 parts by weight of diluent to the mixed slurry and stir for 12 minutes to form a protective plug slurry.
[0052] The protective plug slurry is filled above the cement plug of the abandoned well through the tubing, and the protective plug slurry is left to settle to obtain a protective plug to complete the plugging of the abandoned well.
[0053] The abandoned well plugging method ...
Embodiment 3
[0055] This embodiment provides a plugging method for an abandoned well, the plugging method comprising: lowering an oil pipe into a place 12m above the cement plug of the abandoned well.
[0056] Flush the well with fresh water circulation for 2 weeks.
[0057] The water of 1020 parts by weight, the bentonite of 60 parts by weight, the sodium carbonate of 3 parts by weight, the barite powder of 1050 parts by weight were mixed, and stirred for 35min, after the bentonite, sodium carbonate and barite powder were mixed with water, they hydrated and swelled, A mixed slurry is formed.
[0058] Add 20 parts by weight of diluent to the mixed slurry and stir for 15 minutes to form a protective plug slurry.
[0059] The protective plug slurry is filled above the cement plug of the abandoned well through the tubing, and the protective plug slurry is left to settle to obtain a protective plug to complete the plugging of the abandoned well.
[0060] The abandoned well plugging method pr...