A construction technology and water supply pipe technology, which is applied in the field of large-depth underwater water supply pipe immersed pipe construction technology, can solve problems such as the inability to meet the underwater slotting requirements of immersed pipe construction, shorten the construction period, reduce construction difficulty and cost, and solve the problem of digging deep not enough effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0039] Embodiment 1: An immersed pipe construction process for a large-depth underwater water supply pipe, comprising the following steps:
[0040] Step a, determine the pipeline layout; explore the underwater terrain, select a flat pipeline layout, and pour townships 5 at both ends of the pipeline layout, the township structure is as follows figure 2 , 3 As shown, the town pier 5 is anchored on the underwater bedrock through the anchor rod 8, and the town pier is provided with a guide groove 6 inclined from the shore foundation to the bottom of the water;
[0041] Step b. Pipeline traction: use the empty pipe traction method, take one side of the bank as the construction site, block the front end of the pipeline 1, and use the construction ship to pull the front end of the pipeline along the pipeline layout to the other side of the bank. Simultaneously connect the pipelines in series until the front end of the pipeline is drawn to the shore foundation on the other side, and...
Embodiment 2
[0045] Embodiment 2: A kind of immersed pipe construction technology of deep water bottom water supply pipe, such as figure 1 shown, including the following steps:
[0046] Step a, the pipe layout route is determined; survey the underwater topography, select a flat pipe distribution route with a silt layer of 2-10 meters at the bottom of the water, and pour townships 5 at both ends of the pipe distribution route. The township structure is as follows figure 2 , 3 As shown, the township 5 is anchored on the bedrock of the water bank through the anchor rod 8, and the township is provided with a guide groove 6 inclined from the bank foundation to the water bottom, and a number of counterweight supports are provided on the township to fix the pipeline entering and leaving the water. The counterweight at the end, excavate trenches and lay sand and gravel foundations in the shallow water on both sides of the water area to form a transition section 7, the upper end of the transition...