Construction method of prestressed pipe pile reinforcing system on soft soil

A technology of prestressed pipe piles and construction methods, applied in the direction of soil protection, excavation, sheet pile walls, etc., to achieve the effects of saving materials, ensuring construction quality, and saving costs

Pending Publication Date: 2021-11-19
CHINA CONSTR FIRST DIV GROUP CONSTR & DEV
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] The invention provides a construction method of prestressed pipe pile reinforcement system on soft ground, which is used to solve technical problems such as precise construction of prestressed pipe piles, treatment of soft soil layers, combined application of construction waste, etc.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method of prestressed pipe pile reinforcing system on soft soil
  • Construction method of prestressed pipe pile reinforcing system on soft soil
  • Construction method of prestressed pipe pile reinforcing system on soft soil

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0035] Taking the construction of a coastal area as an example, the soil in this area is soft soil foundation. In order to ensure the normal construction of the building, the soft soil foundation needs to be treated. Such as Figure 1 to Figure 4 As shown, it is processed by prestressed pipe pile reinforcement system on soft ground. The reinforcement system includes a building brick slag layer 2 on the soft soil layer 1, a hydraulic hammer 4 pile driver 3 installed on the building brick slag layer 2, a floor cushion 9 above the building brick slag layer 2, and building bricks The prestressed pipe pile 5 in the slag layer 2 and the soft soil layer 1; the top of the prestressed pipe pile 5 is connected with a cap; the hydraulic hammer 4 of the pile driver 3 has a hydraulic hammer 4 model of HHP14 with an impact mass of 14 tons, and the pipe pile is For PHC500-100AB type, the pile point 8 is B1 type, which increases the rock penetration capacity of pipe piles. Over-excavate and...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a construction method of a prestressed pipe pile reinforcing system on soft soil. The prestressed pipe pile reinforcing system comprises a building brick slag layer located on a soft soil layer, a hydraulic pile hammering machine installed on the building brick slag layer, a bottom plate cushion layer located above the building brick slag layer and prestressed pipe piles penetrating into the building brick slag layer and the soft soil layer. A bearing platform is connected to the tops of the prestressed pipe piles. Through overexcavation of the soft soil layer and treatment of a water body, targeted treatment on the soft soil foundation is facilitated, through overexcavation and replacement of the building brick slag, the requirement for the bearing capacity of the foundation is met, and the requirement for the bearing capacity of pipe pile construction is guaranteed; through the application of the building brick slag layer, on the basis of ensuring the construction elevation of the cushion layer, the moisture of the soft soil layer can be further treated; the building brick slag layer facilitates on-site material taking, and materials are saved; and through construction of the prestressed pipe piles, the construction process is precisely controlled, the pile forming quality is guaranteed, and soft soil can be further reinforced.

Description

technical field [0001] The invention belongs to the technical field of building construction, in particular to a construction method of a prestressed pipe pile reinforcement system on soft ground. Background technique [0002] With the rapid development of the construction industry, most of the middle and high-rise civil buildings, bridges, highways and other foundations gradually adopt pile foundations. In my country's coastal cities, the foundation is soft soil foundation with high water content, and manual excavation piles cannot be used; conventional drilled (punched) hole pouring piles are easy to collapse holes, shrink in diameter, etc., resulting in common quality problems or quality accidents; From the perspective of engineering design and construction, how to deal with the soft soil foundation, and ensure the precise construction of the pile foundation and the effective use of on-site materials is an urgent problem to be solved. Contents of the invention [0003] ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E02D3/00E02D5/24E02D5/58E02D7/10E02D17/04
CPCE02D3/00E02D5/24E02D5/58E02D7/10E02D17/04
Inventor 邢恩王龙丁炜浩曾庆顺杨迪成张东
Owner CHINA CONSTR FIRST DIV GROUP CONSTR & DEV
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products