technical field
[0001] The invention relates to the "pipe advance" part in the "eighteen characters" guideline of the shallow buried underground excavation method used in the construction process of urban tunnels, and is a method for solving the problem of advanced hole formation and support in sand, pebble and boulder layers. Background technique
[0002] The safety of urban tunnel construction is the most important. Safety includes engineering safety and personal safety. The grouting of small conduits in advance (or called short-tube sheds of steel pipes) is the key to the weak surrounding rocks with poor self-stability in underground projects. In the soil body in front of the top, according to a certain spacing, elevation angle and length, after drilling, arrange small advance pipes of Φ32-42mm, and then perform grouting in the pipes to strengthen the soil body. Such as figure 1 shown. After the underground project is excavated forward, the stability of the surrounding ...