Problems solved by technology

[0002] The painting process of the interior and exterior walls of the building determines whether the wall is smooth and beautiful. Unreasonable construction methods will lead to many quality problems, such as cracks after the putty dries, resulting in cracks in the latex paint. The reason is that the putty is too thick or scraped once. Unevenness, unclean treatment of the base layer, dust and sundries in the pits have not been cleaned up, putty cannot take root, etc.; and the surface layer is hollow and cracked. According to the regulations, layered priming and grid construction, due to the fact that the large area of ​​cement mortar is not divided into grids and layers, and the drying shrinkage varies, hollow cracks will be formed; in addition, when making the surface layer, because the base layer is not clean, The base layer is relatively dry, and it will also crack the surface layer

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment

[0018] After the load-bearing or non-load-bearing walls are built according to the above method, paint and paint according to the following steps:

[0019] (1) Cleaning of the base surface of the brick wall: the masonry brick wall surface must be cleaned before painting;

[0020] (2) Grass-roots painting: Before painting, the brick wall must be sprinkled with water and moistened. When the temperature is 5-15°C, water should be sprayed three days in advance. When painting the base layer, first brush the cement slurry one layer, and then use the cement mortar with a ratio of yellow sand and cement of 1:2.5 to paint, and do it twice, the thickness of the first layer is 0.1cm, the thickness of the second layer is 0.08cm, and then use 2 Use a meter-long scraping ruler to smooth the surface of the mortar, and then use a wooden trowel to smooth the mortar surface;

[0021] (3) Putty primer: Putty primer must wait for the mortar strength to reach about 80%. When the temperature is 5~...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

PropertyMeasurementUnit
thicknessaaaaaaaaaa
thicknessaaaaaaaaaa
Login to View More

Abstract

The invention relates to a paint brushing construction method, which sequentially comprises the following steps of brick wall base surface cleaning, base layer brushing, putty priming and surface layer rolling coating. According to a method adopted in the base layer brushing step, firstly, a brick wall base surface is moistened through water spreading, a layer of cement paste is brushed, then, cement mortar is used for brushing, the first layer brushing thickness is 0.08 to 0.1cm, the second layer brushing thickness is 0.05 to 0.08cm, then, the scraping leveling is carried out through a darby, and finally, the floating leveling is carried out through a wood float. According to a method adopted in the putty priming step, the priming is carried out in two layers, the first layer putty priming thickness is 0.3 to 0.5cm, the second layer putty priming is carried out after 22 to 26 hours, the priming thickness is 0.2 to 0.3cm, and two work procedures of grinding leveling machine and sand paper are adopted for grinding leveling after the natural maintenance. According to a method in the surface layer rolling coating step, firstly, a layer of paint is brushed on the putty surfaces primed in the former step, the paint rolling coating is carried out once again after 3 to 5 hours, and then, the maintenance is carried out. The surface layer brushed according to the construction method is smooth, flat and uniform without cracks, in addition, convex-concave corners of wall posts are made into micro arc shapes, the appearance is attractive, simple and compact, and the dust accumulation cannot easily occur.

Description

technical field [0001] The invention relates to the technical field of building construction, in particular to a method for painting interior walls and exterior walls of buildings. Background technique [0002] The painting process of the interior and exterior walls of the building determines whether the wall is smooth and beautiful. Unreasonable construction methods will lead to many quality problems, such as cracks after the putty dries, resulting in cracks in the latex paint. The reason is that the putty is too thick or scraped once. Unevenness, unclean treatment of the base layer, dust and sundries in the pits have not been cleaned up, putty cannot take root, etc.; and the surface layer is hollow and cracked. According to the regulations, layered priming and grid construction, due to the fact that the large area of ​​cement mortar is not divided into grids and layers, and the drying shrinkage varies, hollow cracks will be formed; in addition, when making the surface laye...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E04F13/02E04F13/04
Inventor 陶祖岐
Owner 无锡市康顺节能材料科技有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products