Steel ball special for aerated brick steel mold capsule
A technology of aerated bricks and steel molds, applied in the field of wear-resistant steel balls, which can solve the problems of poor surface quality of wear-resistant steel balls, decline in comprehensive performance, increase of chromium content in wear-resistant steel balls, etc., and achieve the effect of improving product quality
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0038] (2) Heat treatment process: The production process of a special steel ball for aerated brick steel mold capsule is as follows:
[0039] (1) Melting process:
[0040] The first step of smelting: melting in an intermediate frequency induction furnace, adding Si: 0.3Kg, Mn: 1.3Kg, Cr: 18Kg, Mo: 0.3Kg, Ni: 0.5Kg, scrap iron or scrap steel 79.6Kg into the intermediate frequency induction furnace, fully smelting ;
[0041] The second step of pouring: Preheat the metal mold, pour it into the metal mold at a constant temperature, and then cool down to obtain the rough casting; put the rough casting into the heating furnace after unpacking and polishing;
[0042] Quenching: The heating furnace is heated to 650°C, and after holding for 2 hours, it is quenched in a water pool at 1000°C. After 2 hours, the quenching process is repeated once, and then put into the tempering furnace;
[0043] Tempering: The tempering furnace temperature is controlled at 250°C, tempered for 8 hours...
Embodiment 2
[0045] The production process of a special steel ball for aerated brick steel mold capsule is as follows:
[0046] (1) Melting process:
[0047] The first step of smelting: melting in an intermediate frequency induction furnace, adding Si: 2.6Kg, Mn: 2Kg, Cr: 20Kg, Mo: 0.5Kg, Ni: 1Kg, scrap iron or scrap steel 73.9Kg into the intermediate frequency induction furnace, and fully smelted;
[0048] The second step of pouring: Preheat the metal mold, pour it into the metal mold at a constant temperature, and then cool down to obtain the rough casting; put the rough casting into the heating furnace after unpacking and polishing;
[0049] (2) Heat treatment process:
[0050] Quenching: Heat the furnace to 650°C, keep it warm for 4 hours, then quench it in a water pool at 1050°C, repeat the quenching process once after 2 hours, and put it into the tempering furnace;
[0051] Tempering: The temperature of the tempering furnace is controlled at 280°C, tempered for 9 hours, and high ch...
Embodiment 3
[0053] The production process of a special steel ball for aerated brick steel mold capsule is as follows:
[0054] (1) Melting process:
[0055] The first step of smelting: Melting in an intermediate frequency induction furnace, adding Si: 0.4Kg, Mn: 1.8Kg, Cr: 19Kg, Mo: 0.4Kg, Ni: 0.8Kg, scrap iron or scrap steel 77.6Kg into the intermediate frequency induction furnace, fully smelting ;
[0056] The second step of pouring: Preheat the metal mold, pour it into the metal mold at a constant temperature, and then cool down to obtain the rough casting; put the rough casting into the heating furnace after unpacking and polishing;
[0057] (2) Heat treatment process:
[0058] Quenching: the heating furnace is heated to 650°C, and after 3 hours of heat preservation, it is quenched in a pool of 1000°C, and after 2 hours, the quenching process is repeated once, and then put into the tempering furnace;