Process for preparing modified asphalt by using chemical method
A technology of modified asphalt and chemical method, which is applied in the direction of building components, building insulation materials, buildings, etc., can solve problems such as backward technology, imperfect equipment, and unsound production system, and achieve the effect of simple preparation process and short process time
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0029] (1) Weigh 200g of asphalt into a beaker, heat the beaker in an oil bath at 80°C, and stir gently with a glass rod to prevent local overheating;
[0030] ⑵ When the asphalt stops bubbling, stop heating;
[0031] (3) Quickly pour the dehydrated asphalt into the high-speed shearing machine, start the high-speed shearing machine, and set the speed to 300r / min;
[0032] (4) Take 20g of polyvinyl chloride and 5g of cross-linked diene, put them into a grinding tank and grind them into tiny particles;
[0033] (5) Add the collected and ground polyvinyl chloride and cross-linked diene into the shearing machine, and increase the speed of the shearing machine to 600r / min;
[0034] ⑹Shear for 5 minutes to obtain a modified asphalt.
Embodiment 2
[0036] (1) Weigh 500g of asphalt into a beaker, heat the beaker in an oil bath at 90°C, and stir gently with a glass rod to prevent local overheating;
[0037] ⑵ Observe the bubbling of the asphalt, and stop heating when the bubbling stops;
[0038] (3) Quickly pour the dehydrated asphalt into the high-speed shearing machine, start the high-speed shearing machine, and set the speed to 400r / min;
[0039] (4) Take 50g of polyvinyl chloride and 12g of cross-linked diene, put them into a grinding tank and grind them into tiny particles;
[0040] (5) Add the collected and finely ground polyvinyl chloride and cross-linked diene into the shearing machine, and increase the speed of the shearing machine to 700r / min;
[0041] ⑹ Cut for 10 minutes to obtain a modified asphalt.
Embodiment 3
[0043] (1) Weigh 5000g of asphalt and put it into an iron container, heat it in an oil bath at 100°C, and stir it with a wooden stick to prevent local overheating;
[0044] ⑵ Observe the bubbling of the asphalt, and stop heating when the bubbling stops;
[0045] (3) Quickly pour the dehydrated asphalt into the high-speed shearing machine, start the high-speed shearing machine, and set the speed at 500r / min;
[0046] (4) Take 300 g of cross-linked diene and 75 g of cross-linked diene, put them into a grinding tank and grind them into tiny particles;
[0047] (5) Add the collected and finely ground polyvinyl chloride and cross-linked diene into the shearing machine, and increase the speed of the shearing machine to 800r / min;
[0048] ⑹ Cut for 15 minutes to obtain a modified asphalt.
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com