Construction method of large-cross section loess tunnel cave entering shallow buried section

A technology for loess tunnels and construction methods, which is applied to tunnels, tunnel linings, and earthwork drilling and mining, and can solve problems such as complex construction, high cost, and long construction period, and achieve the effects of speeding up construction progress, improving economic benefits, and ensuring stability

Inactive Publication Date: 2015-12-16
THE 5TH ENG CO LTD OF CHINA RAILWAY 25TH BUREAU GRP +1
View PDF5 Cites 30 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Loess tunnels are prone to landslides and large deformations during the excavation of loess tunnels. Improper construction methods for shallow-buried loess tunnels can also cause surface subsidence, which greatly increases the difficulty of tunnel construction in the area.
Although the traditional double-side wall pilot pit method can solve the safety of tunnel construction, its construction is complicated, the construction period is long, and the cost is high; Construction Safety of Sectional Loess Tunnel

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method of large-cross section loess tunnel cave entering shallow buried section
  • Construction method of large-cross section loess tunnel cave entering shallow buried section
  • Construction method of large-cross section loess tunnel cave entering shallow buried section

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0032] Example 1: During the construction of the technical scheme of the present invention, a large section loess tunnel entry shallow buried section of a passenger dedicated line in the western region (mileage DK204+702~DK204+752, buried depth 4~10m) was selected and successfully applied With this method, the main construction procedures are as attached Figure 1~8 Shown.

[0033] The present invention will be further described below in conjunction with the drawings and specific embodiments.

[0034] Step 1. Excavation protection on the side of the cave entrance. Before excavation, measure the edge line of the side slope excavation; make a cut-off gutter 5m away from the excavation line. The slope of the side of the cave entrance is excavated in layers from top to bottom according to the design, with a slope of 1:0.75. After the excavation of the side slope, the 4cm thick C25 concrete was first sprayed to seal it, and Ф22 mortar anchor rods were applied. The length is 3.5m, the ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention relates to a construction method of a large-cross section loess tunnel cave entering shallow buried section. The construction method comprises the following steps of: (1) firstly performing excavation protection on a face-upward slope before the cave entering construction; (2) after the face-upward slope construction in the cave entering position is completed, building a reinforced concrete guide wall; (3) after the construction of the guide wall is completed, beating a long pipe roof for forepoling; (4) constructing a leading conduit for supporting on the basis of the big pipe roof forepoling by matching a sectional-steel steel frame; and (5) using a few-part and ultra-short-step excavation construction method for constructing a tunnel, reinforcing monitoring and measurement during the construction and timely constructing primary supporting and secondary lining. The method has the advantages that the influence of tunnel excavation deformation on the ground surface can be effectively reduced; the tunnel excavation stability of the cave entering shallow buried section is ensured; the construction progress is accelerated; the technical problem of construction of the large-cross section loess tunnel cave entering shallow buried section is solved; the tunnel construction safety is ensured; meanwhile, the investment is reduced; and the economic benefits are improved.

Description

technical field [0001] The invention relates to the field of tunnel construction, in particular to a construction method for a shallow-buried section of a large-section loess tunnel. Background technique [0002] With the implementation of the country's western development strategy, the construction of transportation infrastructure in the western region has achieved unprecedented development. Expressways and railways are rapidly extending to the western region, and more and more traffic tunnels will pass through the western loess region. Loess, as a continental sediment accumulated in the Quaternary system, has the characteristics of large pores, vertical joints and tubular channels. The soil particles are easy to disintegrate when exposed to water, showing strong collapsibility. Loess tunnels are prone to landslides and large deformations during the excavation of loess tunnels. Improper construction methods for shallow-buried loess tunnels can also cause surface subsidence,...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E21D9/04E21D11/00E21D20/02
Inventor 窦世学丁春林赵军张伍星武国春吴科亮李志清
Owner THE 5TH ENG CO LTD OF CHINA RAILWAY 25TH BUREAU GRP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products