Hydropower station rectangular high tower hydraulic climb slip form system and construction method

A construction method and technology of hydropower stations, applied in the direction of formwork/formwork/work frame, tower, building type, etc., can solve the problems of limited formwork turnover times, large investment of operators, large investment of construction raw materials, etc., to save formwork production Quantity, construction work environment safety, and the effect of reducing safety hazards

Inactive Publication Date: 2016-08-10
SINOHYDRO BUREAU 11 CO LTD
View PDF7 Cites 5 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0006] To sum up, in the traditional construction process, operators invest more, the number of formwork turnover is limited, the scaffolding increases with the increase of construction height, the investment of construction raw materials is relatively large, and the next layer can only be poured after the concrete is poured. The construction progress is slow. After the construction is completed, due to the joint problem of the concrete construction joint surface, it is easy to produce quality defects such as misalignment and grout leakage.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Hydropower station rectangular high tower hydraulic climb slip form system and construction method
  • Hydropower station rectangular high tower hydraulic climb slip form system and construction method
  • Hydropower station rectangular high tower hydraulic climb slip form system and construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0053] Embodiments of the present invention will be described in detail below in conjunction with the accompanying drawings. Such as Figure 1 to Figure 5 middle,

[0054] The "open"-shaped elevating frame 1 is a structural form of the sliding template body, and the "open"-shaped elevating frame 1 is the main component that jacks are installed and connected with the enclosure and the template as a whole. The main function of the lifting frame is to control the displacement and deformation of the formwork and enclosure due to the lateral pressure and impact force of the concrete; at the same time, it bears the vertical load acting on the entire formwork and transmits the above load to the jack and the support rod. When the hoist is working, it drives the enclosure, template and operating platform to slide upward together.

[0055] The enclosure truss beam 2 is used to reinforce the sliding formwork panels so that the formwork has sufficient rigidity and stability. Its main f...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a hydropower station rectangular high tower hydraulic climb slip form system and construction method; the system comprises a Chinese character Kai-shape lifting rack, an enclosure truss girder, a F-type lifting rack, jacks, templates, [phi] 48 climb poles, auxiliary disc hooks, 5cm thickness riding track plates, auxiliary discs, maintenance water pipes, to-be-casted concrete, casted concrete, demoulded concrete, a maintenance gate slot, and a gate body; the method comprises the following steps: 1, slip form bodies are processed in a factory to form module members, the members are assembled on site, and the length and weight of the members are proper to transport; 2, module support platform construction; 3, module assembling order. The advantages are that the hydropower station rectangular high tower hydraulic climb slip form system can realize contentious construction, is fast in speed, simple in structure, saves template making quantity, reduces safety troubles, and reduces safety cost.

Description

technical field [0001] The invention relates to a hydraulic climbing sliding form system and a construction method for a rectangular high tower of a hydropower station, and belongs to the technical field of hydropower station construction. Background technique [0002] At present, for vertical reinforced concrete structures, according to the traditional construction technology during construction, the height of each pouring is 2.0-4.0m, and the formwork usually adopts large steel formwork, composite steel formwork, and bamboo plywood formwork. [0003] For example, the patent application number CN201010546376.4 discloses a reliability analysis method for a wind power generation high tower system, which includes the following steps: selecting the external load random parameters of the wind power generation high tower; selecting or generating external loads corresponding to the random parameters; Load; establish the shell element model of the wind power tower system in the ANS...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E04H12/34E04G11/22E04G11/24
CPCE04H12/341E04G11/22E04G11/24
Inventor 董党娄聚会王杰樊瑞钊曲胜辉
Owner SINOHYDRO BUREAU 11 CO LTD