A technology for loess tunnels and construction methods, applied in tunnels, tunnel linings, earthwork drilling and mining, etc., can solve the problems of many construction operations, slow construction progress, low construction efficiency, etc., reduce construction risks and landslides, and ensure construction quality , Improve the effect of construction efficiency
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0021] The embodiments of the present invention will be further described in detail below.
[0022] The construction method of large-section loess tunnel pre-cut groove method of the present invention, its preferred embodiment is:
[0023] Include steps:
[0024] A. Use glass fiber and grout to reinforce the face;
[0025] B. Use pre-grooving equipment to cut grooves along the designed section of the tunnel;
[0026] C. Concrete is immediately poured into the cut groove to form the overall pre-lining of the arch wall of the tunnel, and the two-ring pre-lining is overlapped;
[0027] D. Erect the steel frame and shotcrete in the triangular belt on the pre-lined bell mouth of the upper ring adjacent to the tunnel face;
[0028] E. Under the protection of the pre-lining, use excavators to excavate the full section of the tunnel, determine the amount of reserved deformation according to the ground conditions, and use the anchor bolts at the foot of the wall;
[0029] F. Excava...