Double shield tbm closed ring construction method
A construction method and closed-loop technology, which are applied in earth-moving drilling, wellbore lining, tunnel lining, etc., can solve the problems of "unclosed" effect, unsatisfactory closed-loop production effect, unintuitive construction operation, etc. Filling and adhesion of voids, small loss of fluidity, avoidance of cracks or fissures
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0029] The double-shield TBM closed loop construction method of this embodiment includes the following steps:
[0030] Step 1. Select the following raw materials:
[0031] a. Cement;
[0032] B. colloidal coagulant; said colloidal coagulant is formed by stirring, distilling and pulverizing successively by konjac glucomannan, carbonate, rheological agent, dispersant, early strength agent and water, said The amount of colloidal coagulant is 4% of the cement mass;
[0033] C. sand; the addition of described sand is equal to cement quality;
[0034] d. water; the addition of said water is 35% of the total mass of cement, colloid coagulant and sand;
[0035] In this embodiment, the preparation method of the colloidal coagulant is as follows: firstly add konjac glucomannan, carbonate, rheological agent, dispersant and early strength agent to fully dissolve respectively, and then fully dissolve The obtained konjac glucomannan solution, carbonate solution, rheological agent soluti...
Embodiment 2
[0049] The double-shield TBM closed loop construction method of this embodiment includes the following steps:
[0050] Step 1. Select the following raw materials:
[0051] a. Cement;
[0052] B. colloidal coagulant; said colloidal coagulant is formed by stirring, distilling and pulverizing successively by konjac glucomannan, carbonate, rheological agent, dispersant, early strength agent and water, said The amount of colloidal coagulant added is 5% of the cement mass;
[0053] c. sand; the addition of the sand is 100% of the cement quality;
[0054] d. water; the addition of said water is 30% of the total mass of cement, colloid coagulant and sand;
[0055] In this embodiment, the preparation method of the colloidal coagulant is as follows: firstly add konjac glucomannan, carbonate, rheological agent, dispersant and early strength agent to fully dissolve respectively, and then fully dissolve The obtained konjac glucomannan solution, carbonate solution, rheological agent sol...
Embodiment 3
[0069] The double-shield TBM closed loop construction method of this embodiment includes the following steps:
[0070] Step 1. Select the following raw materials:
[0071] a. Cement;
[0072] B. colloidal coagulant; said colloidal coagulant is formed by stirring, distilling and pulverizing successively by konjac glucomannan, carbonate, rheological agent, dispersant, early strength agent and water, said The amount of colloidal coagulant is 3% of the cement mass;
[0073] c. sand; the addition of the sand is 50% of the cement quality;
[0074] d. water; the addition of said water is 40% of the total mass of cement, colloid coagulant and sand;
[0075] In this embodiment, the preparation method of the colloidal coagulant is as follows: firstly add konjac glucomannan, carbonate, rheological agent, dispersant and early strength agent to fully dissolve respectively, and then fully dissolve The obtained konjac glucomannan solution, carbonate solution, rheological agent solution, ...