Excavation and support method of large cross-section tunnel through fault fracture zone

A tunnel excavation and large-section technology, which is applied in tunnels, tunnel linings, earthwork drilling and mining, etc., can solve the problems of restricted construction period, fast deformation rate of vaults, and large-area encroachment of surrounding rocks.

Active Publication Date: 2018-11-20
CHINA RAILWAY 20 BUREAU GRP
View PDF7 Cites 13 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Especially in the construction process of large-section tunnels crossing fault fracture zones, the vault deformation rate is fast after excavation, the subsidence is too large in a short period of time, and the side walls and arches are twisted and deformed. collapse and other characteristics, in this case, if conventional construction methods and support systems are adopted, such as the step method, three-step method, double-side wall pilot method, CD method, CRD method, etc., the deformation can be controlled very well on the one hand, and on the other hand The construction process is complicated, and the complicated construction method leads to a long construction time and long-term exposure of the surrounding rock, which is likely to cause large-scale encroachment of the surrounding rock, spalling and falling of the shotcrete, and distortion of the steel frame, which further increases the risk of collapse, and the safety and quality cannot be guaranteed. At the same time, it also severely restricts the construction period

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Excavation and support method of large cross-section tunnel through fault fracture zone
  • Excavation and support method of large cross-section tunnel through fault fracture zone
  • Excavation and support method of large cross-section tunnel through fault fracture zone

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0093] Such as figure 1 Shown is a method for excavating and supporting a large-section tunnel crossing a fault fracture zone. The tunnel hole of the constructed large-section tunnel includes a tunnel upper hole body 1 and a tunnel lower hole body located below the tunnel upper hole body 1. The tunnel The upper cave body 1 includes a left pilot tunnel 1-1 and a right pilot tunnel 1-2 on the right side of the left pilot tunnel 1-1, see figure 2 ;

[0094] The initial support structure of the tunnel hole includes a full-section support system for the full-section support of the tunnel hole and a tunnel bolt-net spray support structure for the initial support of the arch wall of the tunnel hole. Between the left pilot tunnel 1-1 and the right pilot tunnel 1-2, there is a temporary support structure for the intermediate partition wall. The temporary support structure for the intermediate partition wall is located in the upper tunnel body 1 of the tunnel and is located Inside th...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses an excavation and support method of large cross-section tunnel through fault fracture zone. The initial support structure of tunnel comprises a whole cross-section support system and the lattice girder and shotcrete support structure of the tunnel. A temporary support structure of middle-partition wall is arranged between a left pilot tunnel and a right pilot tunnel. The actual construction includes the steps: 1, excavation of the upper tunnel body; 2, the judgment of the initial support deformation of the tunnel arch wall and the construction of the replacement arch; 3, excavation of the lower tunnel body. The excavation and support method of large cross-section tunnel through the fault fracture zone has reasonable design, simple construction, and good use effect.Only the upper half section of the tunnel is excavated by the center diaphragm method, and the excavation cross-section is reduced so that the stability of the arch roof is ensured. The whole cross-section support system and the temporary support structure of middle-partition wall are supported by the underpass beam and joined together to form a stable monolithic support system, which can avoid the sinking of the supporting arch and ensure the stability of the initial support effectively. Besides, the construction of replacement arch is conducted on only half cross-section of the tunnel and the cost can be saved, and the construction safety can be ensured.

Description

technical field [0001] The invention belongs to the technical field of tunnel construction, and in particular relates to an excavation and support method for a large-section tunnel crossing a fault fracture zone. Background technique [0002] With the increase of highway transportation volume and the development of infrastructure projects, single-hole, two-lane, multi-lane highway large-section tunnels are becoming more and more common. Compared with single-line small-section tunnel construction, large-section tunnel construction is more likely to cause large-scale subsidence of the vault during excavation. Especially in the construction process of large-section tunnels crossing fault fracture zones, the vault deformation rate is fast after excavation, the subsidence is too large in a short period of time, and the side walls and arches are twisted and deformed. collapse and other characteristics, in this case, if conventional construction methods and support systems are ado...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E21D9/00E21D11/10E21D11/15E21D11/18E21D20/00E21D11/14
CPCE21D9/00E21D9/001E21D11/10E21D11/14E21D11/152E21D11/18E21D20/00
Inventor 郭朋超谭振武郭建才张建升陈耀华李志勇张志潼张佳佳郭瑞李校珂
Owner CHINA RAILWAY 20 BUREAU GRP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products