Asphalt pavement crack sealing repair method
A repair method and asphalt pavement technology, applied in the field of sealants, can solve the problems of low initial strength, temperature sensitivity, easy aging, etc., and achieve the effects of low modulus, high elongation, and stable sealing effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0016] The asphalt pavement crack filling and repairing method of the present embodiment comprises the following steps: a. Carry out milling to the damaged pavement and form the milling groove, when the groove width is 1.3cm, the groove depth is 1.5cm, when the groove width is 3cm, The groove depth is 3cm;
[0017] b. Heat the damaged part of the pavement to 180°C with microwaves, so that the moisture and air in the cracks inside the milling groove will overflow, and fully dry the pavement with a steam pressure pump;
[0018] c. Inject the sealant into the joint filling tank through the joint filling machine, control the height of the filling layer to be about 0.3cm lower than the road surface, and after 3 hours, keep the temperature at 170°C, and then spray it with a spraying amount of 1.6kg / ㎡ SBS modified asphalt is evenly paved on the surface of the milling groove;
[0019] The sealant raw material includes the following components in parts by weight: 30 parts of epoxy res...
Embodiment 2
[0021] The asphalt pavement crack filling and repairing method of the present embodiment comprises the following steps: a. Carry out milling to the damaged pavement and form the milling groove, when the groove width is 3cm, the groove depth is 2.5cm, when the groove width is 6cm, the groove The depth is 5cm;
[0022] b. Use microwaves to heat the damaged part of the road surface to 200°C, so that the moisture and air in the cracks inside the milling groove will overflow, and fully dry the road surface with a steam pressure pump;
[0023] c. Inject the sealant into the joint filling tank through the joint filling machine, control the height of the filling layer to be about 0.3cm lower than the road surface, and after 4 hours, keep the temperature at 190°C, and then spray it with a spraying amount of 1.7kg / ㎡ SBS modified asphalt is evenly paved on the surface of the milling groove;
[0024] The sealant raw material includes the following components in parts by weight: 40 parts ...
Embodiment 3
[0026] The asphalt pavement crack filling and repairing method of the present embodiment comprises the following steps: a. Carry out milling to the damaged pavement and form the milling groove, when the groove width is 2cm, the groove depth is 2cm, when the groove width is 4cm, the groove depth 4cm;
[0027] b. Use microwaves to heat the damaged part of the road surface to 185°C, so that the moisture and air in the cracks inside the milling groove will overflow, and fully dry the road surface with a steam pressure pump;
[0028] c. Inject the sealant into the joint filling tank through the joint filling machine, control the height of the filling layer to be about 0.3cm lower than the road surface, and after 3.5 hours, keep the temperature at 180°C, and then spray it with a spraying amount of 1.6kg / ㎡ SBS modified asphalt is evenly paved on the surface of the milling groove;
[0029] The sealant raw material includes the following components in parts by weight: 30 parts of epox...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com