Annealing process of 1.2746, namely 45NiCrMoV or 4CrNi4MoV die steel
An annealing process and die steel technology, applied in the field of metal heat treatment, can solve the problems of reducing production efficiency and equipment utilization, long annealing time, and high energy consumption, and achieve the effect of shortening turnaround time and improving equipment utilization.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0020] 1.2746 flat steel, the size is 60mm in thickness, 120mm in width, 6.0m in length, and weighs 16.8 tons. After the steel is out of the pit, measure the hardness (HBW) 410, 425, 435;
[0021] Carry out the first annealing: heating with gas in the continuous roller bottom heating furnace, the heating rate is 80°C / h, heating to 780°C for 8 hours; after the heat preservation is completed, slowly cool to 680°C at a speed of 35°C / h and hold for 25 hours , after cooling slowly to 250°C at a rate of 35°C / h, take it out of the furnace and cool to room temperature; the hardness (HBW) is 370, 386, 410.
[0022] Carry out the second annealing: heating with gas in a continuous roller hearth heating furnace, the heating rate is 80°C / h, heating to 630°C for 36 hours; Cool to room temperature; test hardness (HBW) is 270, 276, 280.
Embodiment 2
[0024] 1. 2746 flat steel, with a thickness of 58mm, a width of 118mm, a length of 6.0m, and a weight of 13.7 tons. After the steel is out of the pit, measure the hardness (HBW) 414, 432, 438;
[0025] Carry out the first annealing: heating with gas in a continuous roller bottom heating furnace, the heating rate is 80°C / h, heating to 780°C for 8 hours; after the heat preservation is completed, slowly cool to 650°C at a speed of 40°C / h and hold for 25 hours , after cooling slowly to 230°C at a rate of 30°C / h, take it out of the furnace and cool to room temperature;
[0026] Carry out the second annealing: heating with gas in a continuous roller hearth heating furnace, the heating rate is 80°C / h, heating to 630°C and keeping it for 36h; Cool to room temperature; test hardness (HBW) is 268, 270, 275.
Embodiment 3
[0028] 1.2746 flat steel, the size is 44mm in thickness, 110mm in width, 6.0m in length, and weighs 12.6 tons. After the steel is out of the pit, measure the hardness (HBW) 411, 430, 437;
[0029] Carry out the first annealing: heating with gas in a continuous roller bottom heating furnace, the heating rate is 80°C / h, heating to 740°C for 6 hours; after the heat preservation is completed, slowly cool to 650°C at a speed of 40°C / h and hold for 30 hours , after cooling slowly to 225°C at a rate of 30°C / h, take it out of the furnace and cool to room temperature; the hardness (HBW) is 380, 388, 410.
[0030] Carry out the second annealing: heating with gas in a continuous roller hearth heating furnace at a heating rate of 80°C / h, heating to 650°C for 36 hours; Cool to room temperature; test hardness (HBW) is 266, 269, 275.