Method for detecting and evaluating irregularity of temporary transportation track of overlong TBM (Tunnel Boring Machine) tunnel under construction

A technology of irregularity and transport track, which is applied in the field of irregularity detection of temporary transport track of super-long TBM tunnel under construction, which can solve the problems of long database generation time, high processing cost, track irregularity, etc., and reduce manual inspection. , The effect of reducing the risk of driving and preventing the deformation of the track

Pending Publication Date: 2022-04-05
XINJIANG IRTYSH RIVER BASIN DEV ENG CONSTR ADMINISTRATION +1
View PDF7 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

The materials and personnel required during the TBM tunnel construction must be transported to the working face by rail trains, but most of the tunnel constructions erect temporary tracks for vehicle transport, and the temporary tracks are mainly used as tracks for material transport during the construction process. The speed is low, and the laying quality requirement is lower than that of the track during railway operation, but the irregularity of the temporary track also directly affects the transportation efficiency of the rail train, and even production safety, such as accidents such as the derailment of the rail train
[0003] Since the temporary track is far inferior to the laying quality of railway tracks, the existing track detection methods cannot directly detect and evaluate the irregularity of the temporary track. Meter rulers are used to determine the height error of the track joints, and most of them are manually inspected from time to time during use, which is not only inefficient, but also has poor detection results. It cannot detect the unevenness of the track in a timely and effective manner, which directly affects the rail vehicles. safe operation of
[0004] In the published patent literature, the application number is 2021104610158, and the patent named track irregularity detection and evaluation system, method, electronic equipment and rail vehicle discloses a method of obtaining track irregularity value through three-dimensional data of each measurement point The method, the design includes multiple electronic modules, and the degree of automation is high, but the applicant believes that this technology has the disadvantages of huge data and high cost, and is not suitable for general application, especially not suitable for the detection of irregularity of temporary transport tracks in TBM tunnels
After all, the characteristics of the temporary transportation track in the TBM tunnel are: 1. The chief factory director, if summed up at a single point, the amount of data is large and the processing cost is high, and one of the characteristics of the temporary track is to reduce the cost under the premise of ensuring transportation; 2. The data in the basic data pool is too large, and the database generation time is long, which does not meet the characteristics of short-term assembly of temporary tracks and production as soon as possible
[0005] To sum up, that is to say, the main problem to be solved first is that there is an irregularity measurement technology that is too expensive and not suitable for temporary tracks, and conventional technology cannot guarantee the safety of TBM tunnel construction material transportation

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Method for detecting and evaluating irregularity of temporary transportation track of overlong TBM (Tunnel Boring Machine) tunnel under construction
  • Method for detecting and evaluating irregularity of temporary transportation track of overlong TBM (Tunnel Boring Machine) tunnel under construction

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0035] Including the following steps:

[0036] (1) Acquisition equipment installation: rail vehicle vibration sensors are installed on the left and right sides of the train to be detected, odometers are installed on the wheels of the testing machine and next to the vibration sensors, and data acquisition devices are installed on the vehicle console. The input end of the data acquisition device is connected to the vibration sensor and the odometer, the output end of the data acquisition device is connected to the vehicle-mounted terminal, and the vehicle-mounted terminal is connected to the display and analysis module, and the vehicle-mounted terminal, the display and analysis module are installed in the locomotive cab;

[0037] (2) Data acquisition: The tested vehicle runs on the initially laid temporary track at different speeds, obtains the amplitude of the vehicle passing the track joint under different speed v and corresponding acceleration as the initial value, establishe...

Embodiment 2

[0063] The principle of this embodiment is the same as that of Embodiment 1, the specific difference is that the transport vehicle includes a multi-section transport platform, at least the wheels of the front and rear platforms are respectively equipped with data acquisition devices, and the detection is mainly based on the data acquisition device under the first platform, but When in step (3), the evaluation of the roughness of each joint also includes a post-verification step when f / v>0.8 [f / v], △f>0.8[△f], the post-verification step includes Extract the information of the coordinate segment corresponding to the path of the data acquisition device installed at the rear of the vehicle, and extract the f / v and △f of the joint roughness evaluation, if f / v>0.8 [f / v], △f>0.8[△f ] Judgment to continue to reduce the speed, in other cases, keep the speed stable output until the end of the transportation cycle. This design is mainly aimed at the situation that the transport vehicles ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention provides a method for detecting the irregularity of a temporary transportation track of an overlong TBM (Tunnel Boring Machine) tunnel under construction, which is applied to a track irregularity detection evaluation system and aims to solve the problem of low detection capability of track irregularity detection in the prior art, and comprises the following steps of: (1) running a rail train with a sensor on an initially paved temporary track according to different speeds; acquiring amplitudes of vehicles passing through track joints under different vehicle speed working conditions as initial values, and establishing a standard database; (2) acquiring data such as speed, amplitude, mileage and the like during operation of the rail train, comparing and analyzing the data with a standard database, and evaluating the irregularity of each contact, each section of rail and each kilometer of rail; and (3) reminding a driver of vehicle deceleration through a vehicle-mounted display device, and reminding a manager of temporary track maintenance through a background data report. The method has the advantages that real-time detection and evaluation can be achieved through double-track measurement, manual inspection is reduced, the detection frequency is improved, and the temporary railway vehicle driving risk is effectively reduced.

Description

technical field [0001] The invention relates to the technical field of safe transportation of super-long TBM tunnel materials, in particular to a method for detecting irregularities of temporary transportation tracks of super-long TBM tunnels under construction. Background technique [0002] Tunnel engineering construction has gradually developed towards the direction of ultra-long-distance construction, and TBM is more and more widely used as a rapid construction equipment for long tunnels. The materials and personnel required during the TBM tunnel construction must be transported to the working face by rail trains, but most of the tunnel constructions erect temporary tracks for vehicle transport, and the temporary tracks are mainly used as tracks for material transport during the construction process. The speed is low, and the laying quality requirements are lower than that of the track during railway operation, but the irregularity of the temporary track also directly aff...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): B61K9/08B61D15/08
CPCY02T90/00
Inventor 郭新强李治国肖逸飞白亮李铭杰曾垂刚王发民王恒超王军李宏波汤伟华张恒吕乾乾
Owner XINJIANG IRTYSH RIVER BASIN DEV ENG CONSTR ADMINISTRATION
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products