Early strengthening flyash three-slag road forndation material
A roadbed material, fly ash technology, applied in the field of fly ash three-slag roadbed materials, can solve the problems of inability to be widely used, high cost, long maintenance period, etc.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0005] Implementation 1: Get 65 kilograms of crushed stone, 24 kilograms of fly ash, 10 kilograms of slaked lime, the particle size of the crushed stone is 40-70MM, crushed stone, fly ash and slaked lime are the weight of dry material, stir, and then mix 1 kg of Accelerator (prepared by two parts of high calcium ash and one part of sodium sulfate) and mixed with 37 kg of water, and the total water content was controlled at about 27%.
Embodiment 2
[0006] Implementation 2: Get 73 kilograms of crushed stone, 18 kilograms of fly ash, and 8 kilograms of slaked lime. The particle size of the crushed stone is 5-30MM. Accelerator (prepared by two parts of high calcium ash and one part of sodium sulfate) and mixed with 37 kg of water, and the total water content was controlled at about 27%.
Embodiment 3
[0007] Implementation 3: get 80 kilograms of crushed stone, 14 kilograms of fly ash, 5 kilograms of slaked lime, the particle diameter of crushed stone is 5-30MM, crushed stone, fly ash and slaked lime are dry weight, stir, then 1 1kg of accelerator (prepared with 2 parts of high calcium ash and 1 part of sodium sulfate) and add 37 kg of water, mix and stir, and control the total water content at about 27%.
[0008] The moisture content of the above-mentioned early-strength fly ash three-slag roadbed material should be controlled not to exceed 5 percentage points of the standard after mixing, and the moisture content should not exceed 8 percentage points of the standard in hot days, so as to ensure that the moisture content is close to the optimum during construction and rolling. , should be paved as evenly as possible on the construction site, generally 15-25CM thick, and compacted with tire rollers or vibratory rollers.
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com