Construction method for full-casing long spiral bored piles

A technology of auger drilling and construction method, which is applied in the direction of sheet pile wall, foundation structure engineering, construction, etc. It can solve the problems of mud discharge pollution, thick residue at the bottom of the hole, and low construction efficiency, and achieve low construction noise and high pile quality Good, fast drilling effect

Inactive Publication Date: 2016-11-23
上海腾尚基础工程有限公司
View PDF7 Cites 14 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, the construction efficiency of the above-mentioned equipment is low. During the hole forming process, mud protection walls are required to prevent the hole from collapsing, and there is a problem of mud discharge pollution; the verticality of the pile body is only 1 / 150, and the construction noise is large. Process disadvantages such as neck and hole bottom thick residue

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method for full-casing long spiral bored piles
  • Construction method for full-casing long spiral bored piles
  • Construction method for full-casing long spiral bored piles

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0063]Below in conjunction with specific embodiment, further illustrate the present invention. It should be understood that these examples are only used to illustrate the present invention and are not intended to limit the scope of the present invention. In addition, it should be understood that after reading the teachings of the present invention, those skilled in the art can make various changes or modifications to the present invention, and these equivalent forms also fall within the scope defined by the appended claims of the present application.

[0064] In this embodiment, a full casing long helical drilling rig is used for construction. The full casing long auger drilling rig is a purchased product, which is a SZ80-35 hydraulic multifunctional drilling rig produced by Shanghai Jintai Engineering Machinery Co., Ltd.

[0065] figure 1 The construction flow chart of the full-sleeve length helical bored pile provided for this embodiment, the specific steps of the construct...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention provides a construction method for full-casing long spiral bored piles. The method includes the steps that firstly, a casing pipe and a spiral drill pipe of a full-casing long spiral drilling machine simultaneously rotate and sink so as to form a hole after being aligned with a pile position; secondly, the drilling machine is moved to the next pile for hole formation operation, and meanwhile, adhering soil on the inner wall of the casing pipes in the formed hole is removed in a brushing mode through a wall brushing device; thirdly, a reinforcement cage is hoisted into the hole, concrete is poured into the reinforcement cage, and concrete pouring is stopped after the concrete is poured to the top elevation of the reinforcement cage; fourthly, a cage pressing device is hoisted into the casing pipe, and concrete pouring continues; fifthly, a pile machine is located in place, and a drill bit is elevated to the cage pressing device to press the reinforcement cage; and finally, the casing pipe is lifted and pulled out, the cage pressing device is removed, and pile forming is completed. The construction method provided by the invention is high in construction efficiency, the wall of a formed pile hole is regular in shape, a pile body is high in perpendicularity, and the pile forming quality is good; soil squeezing, hole collapse and vibration are avoided, and construction noise is low; and slurry pollution in the construction process is avoided, the outward slurry transport cost is reduced, the cost is reduced, and the construction method is environmentally friendly.

Description

technical field [0001] The invention relates to a construction method of a full-sleeve length helical bored pile used in the construction of bored piles, occlusal piles and the like in the technical field of civil engineering (pile foundation). Background technique [0002] The cast-in-situ pile system refers to the piles formed by forming pile holes in the foundation soil by means of mechanical drilling, steel pipe extrusion or manual excavation on the project site, and placing steel cages in them and pouring concrete. According to different hole-forming methods, cast-in-situ piles can be divided into several categories such as immersed tube cast-in-place piles, bored cast-in-place piles, and hole-dug cast-in-situ piles. [0003] At present, the conventional machinery and equipment for bored pile construction are rotary drilling rigs and GPS drilling rigs. However, the construction efficiency of the above-mentioned equipment is low. During the hole forming process, mud pro...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E02D5/38E02D5/56E02D5/66E02D15/08
CPCE02D5/38E02D5/385E02D5/56E02D5/665E02D15/08
Inventor 陈刚金一郎陈晨光沈新波
Owner 上海腾尚基础工程有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products