Construction method of bored and bottom-compact cement grouting pile

A construction method and technology in drilling, which is applied in sheet pile walls, foundation structure engineering, construction, etc., can solve the problems that the bearing capacity of cast-in-place piles cannot meet the construction standards, etc., so as to improve the bearing capacity of piles and the resistance of pile ends , to ensure the overall effect

Inactive Publication Date: 2018-10-19
邹延辉
View PDF2 Cites 1 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] The present invention aims to solve the problem that existing underwater pouring piles with virtual soil at the pile ends and post-grouting piles cannot guarantee that the grouting of each bearing layer reaches the expected standard, resulting in the bearing capacity of the pouring piles not reaching the construction standard, and further provides a Construction Method of Drilled Bottom Grouting Pile

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

specific Embodiment approach 1

[0025] Specific implementation mode one: the construction method of the bored rammed bottom grouting pile described in this implementation mode is realized according to the following steps:

[0026] Step 1. Drilling: Use a long auger to drill the hole;

[0027] Step 2. One-time grouting: inject cement slurry into the retaining wall from the bottom of the auger drill to form holes, control the grouting pressure of the cement slurry to 1-5mpa, control the water-cement ratio of the cement slurry to 0.6-0.8, and the aperture range to 300-1000mm;

[0028] Step 3. Drill bit lifting: ensure that the lifting speed of the drill bit of the auger drill is lower than the grouting speed, until the drill bit of the auger drill is completely lifted out of the borehole to complete a grouting;

[0029] Step 4. Bottom tamping: insert prefabricated high-strength concrete components into the borehole, and use prefabricated high-strength concrete components to perform high-frequency vibratory comp...

specific Embodiment approach 2

[0031] Specific implementation mode 2: In step 2 of this implementation mode, the grouting pressure of the cement slurry is controlled to be 2-4 mpa during the primary grouting.

[0032] In this way, the cement slurry has a cementation effect, and the pressure injection of the cement slurry can increase the resistance of the side of the pile and the resistance of the pile end. Other components and connections are the same as those in the first embodiment.

specific Embodiment approach 3

[0033] Specific implementation mode three: control the grouting pressure of the cement slurry to 3mpa during the first grouting in the second step of this embodiment.

[0034] In this way, the cement slurry has a cementation effect, and the pressure injection of the cement slurry can increase the resistance of the side of the pile and the resistance of the pile end. Other components and connections are the same as those in the second embodiment.

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention provides a construction method of a bored and bottom-compacted cement grouting pile, relates to a pile foundation construction method, and aims at solving the problems that the end of anexisting underwater cast-in-place pile is subjected to loosened soil, and each bearing stratum cannot be grouted based on the expected standard, and thus the bearing capacity of a cast-in-place pilecannot reach the construction standard. The method comprises the steps of 1, boring; 2, pouring cement paste through the bottom part of a spiral drilling machine to protect the wall and form a pore; controlling the cement paste grouting pressure to be 1-5mp and controlling the water-cement ratio of the cement paste to be 0.6-0.8; 3, ensuring that the lifting speed of a drill bit of the spiral drilling machine is less than the grouting speed until the whole drill bit of the spiral drilling machine is completely lifted from the pore, and thus finishing first grouting; 6, inserting a precast high-strength concrete component into a bore; and compacting the loosened soil at the bottom of the pore through the precast high-strength concrete component in a high-frequency vibrating impacting manner; and 5, performing the second grouting, namely, inserting a pipe in a clearance between the pore and the precast high-strength concrete part; and filling the cement paste into the whole clearance between the pore and the precast high-strength concrete component. The method is applicable to pile foundation construction.

Description

technical field [0001] The invention relates to a construction method of a bored bottom rammed grouting pile. Background technique [0002] With the rapid development of my country's construction industry, the requirements for the bearing capacity of building foundations are getting higher and higher, the foundation forms are also various, and concrete pouring piles are widely used. [0003] At present, in the construction of underwater cast-in-situ pile foundation, due to the specific structure of the head of the drill rig's auger, a part of virtual soil will remain at the bottom of the long auger hole, resulting in a great loss of pile tip resistance. The existing post-grouting construction method cannot guarantee that the grouting of each bearing layer can reach the expected standard, resulting in the bearing capacity of the cast-in-situ pile not reaching the expected construction standard. Contents of the invention [0004] The present invention aims to solve the prob...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E02D5/50E02D7/00
CPCE02D5/50E02D7/00
Inventor 王常青邹延辉
Owner 邹延辉