Grouting method for dealing with tunnel collapse
A technology for tunnels and grouting pipes, which is applied in tunnels, tunnel linings, mining equipment, etc., and can solve problems such as pipe jams, large engineering quantities, and controllability of crossing landslides cannot be guaranteed.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0024] Example 1: A case of landslide treatment at the outlet of Daying River Diversion Tunnel in Yunnan at 0+107.5~0+118
[0025] 1. Project overview:
[0026] The standard excavation section of the Dayingjiang diversion tunnel chamber is 10m*11.5m, and the buried depth of the cavern near the slope is relatively shallow. There is no bedrock exposed above the elevation EL 673m, and the surrounding rock of the cavern is composed of gravel, sandy clay and boulders, with a loose structure and complex geological conditions. The diversion tunnel is formed by layered excavation. The excavation height of the upper tunnel is about 4.5m, and the excavation height of the middle and lower tunnels is about 3.5m. When the upper tunnel was penetrated and the pioneer trench of the lower tunnel was excavated to stake number 0+107.5m, groundwater leaked from the near slope, and then the vertical side wall of the retained rock mass collapsed, and the upper supporting steel support was deformed...
Embodiment 2
[0042] Example 2: The case of traffic tunnel on the left bank of Jinping I Hydropower Station.
[0043] 1. Brief introduction of the project:
[0044] The cross-section of the traffic tunnel on the left bank of Jinping I Hydropower Station is a city gate tunnel, and the size after lining is 10m×8.5m (width×height). When the tunnel was excavated to the section under the jurisdiction of the S8 branch tunnel, due to the loose phyllite strata, the tunnel that had penetrated had a landslide. The landslide was a loose coal-like powder, and it became a mud-like structure after repeated rolling by vehicles. . In the early stage, the landslide was treated with a forced slag removal plan, and the landslide slag was transported about 3000m³, but only 1 day after the landslide was forcibly passed through, a large-scale landslide occurred again, and the landslide hole was about 12m long. The body is piled up to a height of more than 5m above the top of the cave.
[0045] Two, adopt the ...
Embodiment 3
[0047] Example 3: A case of diversion tunnel on the left bank of Jinping I Hydropower Station
[0048] 1. Brief introduction of the project:
[0049] The section of the diversion tunnel on the left bank of Jinping I Hydropower Station is a city gate type, and the size after lining is 15×19m (width×height). The length of the cave body is 1214.359m, and the elevations of the entrance and exit floor are 1638.50m and 1634.00m respectively. The entire diversion tunnel is arranged according to double bends, and is composed of the inlet diversion section, the sluice chamber section, the gradual transition section, the tunnel body section, the plug section, the tunnel body section and the outlet drainage section. The excavation of the cave body is divided into three layers for drilling and blasting excavation. During the excavation of each layer, anchoring and shotcreting are carried out in time according to the surrounding rock conditions. The shotcrete is 10-15cm thick steel fiber ...
PUM
Property | Measurement | Unit |
---|---|---|
Length | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com