Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Grouting method for dealing with tunnel collapse

A technology for tunnels and grouting pipes, which is applied in tunnels, tunnel linings, mining equipment, etc., and can solve problems such as pipe jams, large engineering quantities, and controllability of crossing landslides cannot be guaranteed.

Active Publication Date: 2018-10-26
CHINA HYDROPOWER ELEVENTH ENG BUREAU ZHENGZHOU CO LTD +1
View PDF4 Cites 9 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] In the advance support method of large pipe shed grouting support, the pipe shed drilling rig is used to first drive the steel flower pipes with a diameter of Φ108~Φ189 into the landslide body along the top of the tunnel, and the drilling angle is controlled at 5-10 degrees, and then through the pipe shed on the pipe shed Hole grouting, if necessary, supplemented by a small pipe to adopt a larger external insertion angle to further increase the grouting range of the upper part of the pipe shed grouting; when using a large pipe shed grouting advance support, the lock must be made before the collapse section to prevent landslides Section expansion, the distance between the pipe shed is generally 20cm, and it is arranged along the tunnel arch at 120-180 degrees. The top of the tunnel is expanded to facilitate the arrangement of the pipe-shelf drilling rig for construction, but there is still a danger of expanding the collapsed tunnel section due to the expansion of the cavern adjacent to the collapsed section
[0005] For the above two methods, regardless of whether it is grouting anchorage or large pipe shed grouting, if the anchor rod or pipe shed is driven into the loose body, there may be multiple occurrences of pipe jamming or failure of normal construction.
[0006] The collapse pit grouting method directly injects grout into the landslide body at the surface collapse pit. The grouting range is enlarged and the cost is high. For example, if the distance between the surface collapse pit and the top of the tunnel is large, it is difficult for the grouting slurry to seep down to the top of the cave, for example, the grout cannot reach At the top of the tunnel, it cannot form a consolidation ring near the top of the cave. When cleaning the slag, a large amount of loose slag will slide down. Difficulty, and the controllability of crossing landslides cannot be guaranteed

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0024] Example 1: A case of landslide treatment at the outlet of Daying River Diversion Tunnel in Yunnan at 0+107.5~0+118

[0025] 1. Project overview:

[0026] The standard excavation section of the Dayingjiang diversion tunnel chamber is 10m*11.5m, and the buried depth of the cavern near the slope is relatively shallow. There is no bedrock exposed above the elevation EL 673m, and the surrounding rock of the cavern is composed of gravel, sandy clay and boulders, with a loose structure and complex geological conditions. The diversion tunnel is formed by layered excavation. The excavation height of the upper tunnel is about 4.5m, and the excavation height of the middle and lower tunnels is about 3.5m. When the upper tunnel was penetrated and the pioneer trench of the lower tunnel was excavated to stake number 0+107.5m, groundwater leaked from the near slope, and then the vertical side wall of the retained rock mass collapsed, and the upper supporting steel support was deformed...

Embodiment 2

[0042] Example 2: The case of traffic tunnel on the left bank of Jinping I Hydropower Station.

[0043] 1. Brief introduction of the project:

[0044] The cross-section of the traffic tunnel on the left bank of Jinping I Hydropower Station is a city gate tunnel, and the size after lining is 10m×8.5m (width×height). When the tunnel was excavated to the section under the jurisdiction of the S8 branch tunnel, due to the loose phyllite strata, the tunnel that had penetrated had a landslide. The landslide was a loose coal-like powder, and it became a mud-like structure after repeated rolling by vehicles. . In the early stage, the landslide was treated with a forced slag removal plan, and the landslide slag was transported about 3000m³, but only 1 day after the landslide was forcibly passed through, a large-scale landslide occurred again, and the landslide hole was about 12m long. The body is piled up to a height of more than 5m above the top of the cave.

[0045] Two, adopt the ...

Embodiment 3

[0047] Example 3: A case of diversion tunnel on the left bank of Jinping I Hydropower Station

[0048] 1. Brief introduction of the project:

[0049] The section of the diversion tunnel on the left bank of Jinping I Hydropower Station is a city gate type, and the size after lining is 15×19m (width×height). The length of the cave body is 1214.359m, and the elevations of the entrance and exit floor are 1638.50m and 1634.00m respectively. The entire diversion tunnel is arranged according to double bends, and is composed of the inlet diversion section, the sluice chamber section, the gradual transition section, the tunnel body section, the plug section, the tunnel body section and the outlet drainage section. The excavation of the cave body is divided into three layers for drilling and blasting excavation. During the excavation of each layer, anchoring and shotcreting are carried out in time according to the surrounding rock conditions. The shotcrete is 10-15cm thick steel fiber ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

PropertyMeasurementUnit
Lengthaaaaaaaaaa
Login to View More

Abstract

The invention relates to a grouting method for dealing with tunnel collapse which comprises the following steps: (1) directly sending two grouting pipes from an opening of a collapsed section into a collapsed slag body, controlling the grouting point to be 5 to 6 meters above the top of the opening, injecting the slurry into the loose body. During the grouting process, the slurry is lowered and wrapped by the grouting point, and the lower loose body is consolidated. As the slurry is solidified in the lower part and the liquid level of the slurry in the slag body is gradually raised to the pulping point, completing the wrapping and the consolidation of the loose body below the pulping point; (2) using the traditional soil arching effect principle to consolidate the loose body of the top arch of the collapsed section, that is, after the consolidation of the loose body in the range of 5 to 6 meters above the top of the opening, excavating the top of the tunnel of the collapsed section into an arch shape, and bearing the load of the upper loose body by using the arch effect; (3) after completing the loose ring reinforcement of 5 to 6 meters at the top of the opening, according to the supporting method of the V-type surrounding rock, the steel support made of the I-shaped steel and the top arch excavation work surface are firmly fixed every 0.5 meter, jointly bearing the load of thetop arch. The aim of the grouting method is to overcome the defects existing in the prior three traditional grouting methods and to provide a fast, efficient and safe method for grouting tunnel collapse.

Description

technical field [0001] The invention relates to the field of tunnel engineering, in particular to a method for treating tunnel collapse by using grouting. Background technique [0002] After the existing tunnel landslides accumulate loose bodies on the operation face, most of the loose bodies are reinforced by grouting, and anchoring methods are adopted, such as grouting and anchoring method, large pipe shed grouting advance support method and collapse Pit grouting method. [0003] Most of the grouting anchoring methods are completed by hollow self-advancing anchor rods, using the drill bit that comes with the hollow self-advancing anchor rods to drill holes, and embedding them in the landslide body as the next grouting pipe. Control it between 15-30 degrees, and then use shotcrete to seal the tunnel face, then use medium and high pressure grouting method for grouting; during the process of drilling the hollow anchor rod into the landslide body, if there is a If there is a...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E21D11/10E21D9/00
CPCE21D9/001E21D11/10
Inventor 陈敦刚陈文娟
Owner CHINA HYDROPOWER ELEVENTH ENG BUREAU ZHENGZHOU CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products