Cut-off protection system and cut-off operation method of multi-stage ship lock water delivery valve
A technology for protection systems and valves, which is applied in the field of cut-off protection systems for multi-stage ship lock water delivery valves, and can solve problems such as suspension of the entire line of ship locks, increased suspension time, and increased maintenance period
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0040] The preferred solution is as figure 1 As shown, a cut-off protection system for multi-stage ship lock water delivery valves includes a centralized control system, a local electrical control system and a local hydraulic control system. The local hydraulic control system includes an isolation ball valve, and the cut-off protection system also includes a travel switch. The travel switch is used to detect the travel position of the isolation ball valve. The travel switch is electrically connected to the local electrical control system and the valve closing relay, and the valve closing relay is electrically connected to the local electrical control system.
[0041]The centralized control system is composed of a centralized control unit (abbreviated as a centralized control unit), an operator station, a data and communication server, and an industrial TV monitoring system. , to issue a control order to the local control station to complete the operation process of the ship l...
Embodiment 2
[0049] In the preferred scheme such as figure 2 As shown, the cut-off operation method of the cut-off protection system of the multi-stage ship lock water delivery valve includes the following steps:
[0050] Preparation:
[0051] A. Confirm the maintenance requirements of the water delivery valve, and handle the repair contact list in time.
[0052] B. The construction unit handles the special work ticket for the maintenance and repair of water delivery valves.
[0053] C. The construction unit carries out the transfer of the slab inspection door and boom, and the site construction is ready.
[0054] D. The construction unit fills in the application column of the water delivery valve removal confirmation form, and after contacting the relevant person in charge to sign and approve, the operation management personnel removes the water delivery valve on this side during the operation interval, and reports to the navigation command center.
[0055] The following operations sh...