An optimization method and technology for tight gas, applied in wellbore/well components, design optimization/simulation, earth-moving drilling, etc., can solve the problems of lag in understanding, difficult to consider the impact of gas well production, poor reliability, etc., and achieve accurate results. Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0044] This embodiment provides a method for optimizing the opening time of intermittent wells in tight gas reservoirs, including the following steps:
[0045] S1, determine the optimization goal: the optimization goal of opening time is to maximize the average daily gas production in the intermittent period;
[0046] S2, analyze and verify the feasibility of maximizing the daily average gas production in the intermittent period as the optimization goal of well opening time;
[0047] S3, call real-time production data: use the real-time production data system to call the absolute production time and instantaneous flow data of the gas well with an hour as the time period;
[0048] S4, calculate the well opening time and intermittent cycle production time at different time points: the cumulative well production time of the gas well is taken as the well opening time, and the sum of the accumulated shut-in time before well opening and the well opening production time is taken as t...
Embodiment 2
[0055] On the basis of Example 1, further, the method of analyzing and verifying the feasibility of maximizing the daily average gas production in the intermittent period as the optimization goal of the opening time is to establish the calculation of the average daily gas production in the intermittent period according to the ARPS decline theory The theoretical model, and through extreme value analysis, determine the maximum daily average gas production and the timing of its occurrence in the intermittent period, and verify its feasibility.
[0056] Specifically, the method for analyzing and verifying the feasibility of maximizing the average daily gas production in the intermittent period as the goal of optimizing the opening time includes the following steps:
[0057] S201, according to the ARPS decline theory, it is determined that the cumulative gas production of depleted declining gas wells has the following relationship with the production time:
[0058] where q t is ...
Embodiment 3
[0071] Taking gas well A in the Shenmu gas field as an example, the well was initially shut down for 70 hours and opened for 168 hours intermittently, and the average daily gas production during the intermittent period was 2,732 million cubic meters per day. The optimization method is used to optimize the opening time of intermittent wells in tight gas reservoirs, including the following steps:
[0072] Step 1) Determine the optimization goal. It is proposed that the maximum daily average gas production in the intermittent period is the optimization goal of the well-opening time, where the intermittent period is the sum of the well-opening time and the well-shut-in time before the well-opening.
[0073] Step 2) Analyze the feasibility of taking the average daily gas production in the intermittent period as the optimization target of opening time. Considering that the production decline of gas wells in tight gas reservoirs is mainly depletion decline, based on the ARPS decline...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com