Floury soil improving method
A technology of silt and micro-silica fume, which is applied in the field of expressway subgrade filling, can solve the problems of high cost of improvement, low mechanical properties, and restrictions on the wide application of low liquid limit silt, so as to ensure strength, reduce permeability and compression and brittleness, improving unconfined compressive strength and water stability
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0018] A method for improving silt, characterized in that: comprising the steps of:
[0019] S1, take each component by weight part:
[0020] 80 parts of low liquid limit silt; 2.4 parts of cement; 3.2 parts of lime; 2.4 parts of lignin; 0.3 parts of sodium diethylene triamine pentacarboxylate; 0.4 parts of polyol; Powder 1.28 parts;
[0021] S2. Place the weighed cement, lime, and fly ash in a high-speed mixing mixer, and after stirring for 0.5h, spray lignin, sodium diethylenetriaminepentacarboxylate, polyhydric alcohol, microsilica powder and Acrylic emulsion, the spraying time of each raw material is controlled at 20 minutes, after the addition is completed, the mixture is obtained;
[0022] S3. Mix the obtained mixture with the weighed low liquid limit silt, add water and stir for 30 minutes to obtain the roadbed filler, and the water content of the roadbed filler is 12% to 15%.
Embodiment 2
[0024] A method for improving silt, characterized in that: comprising the steps of:
[0025] S1, take each component by weight part:
[0026] 100 parts of low liquid limit silt; 5 parts of cement; 6 parts of lime; 5 parts of lignin; 0.5 parts of sodium diethylenetriamine pentacarboxylate; 1 part of polyol; 2.4 parts of powder;
[0027] S2. Put the weighed cement, lime, and fly ash in a high-speed mixing mixer, and after stirring for 1 hour, spray lignin, sodium diethylenetriaminepentacarboxylate, polyhydric alcohol, microsilica fume, and acrylic acid in sequence while stirring Emulsion, the spraying time of each raw material is controlled within 30 minutes, after the addition is completed, the mixture is obtained;
[0028] S3. Mix the obtained mixture with the weighed low liquid limit silt, add water and stir for 45 minutes to obtain the roadbed filler, and the water content of the roadbed filler is 12%-15%.
Embodiment 3
[0030] A method for improving silt, characterized in that: comprising the steps of:
[0031] S1, take each component by weight part:
[0032] 90 parts of low liquid limit silt; 3.7 parts of cement; 4.6 parts of lime; 3.7 parts of lignin; 0.4 parts of sodium diethylene triamine pentacarboxylate; 0.7 parts of polyol; 1.8 parts of powder;
[0033] S2. Place the weighed cement, lime, and fly ash in a high-speed mixing mixer, and after stirring for 0.75h, spray lignin, sodium diethylenetriaminepentacarboxylate, polyhydric alcohol, microsilica powder and Acrylic emulsion, the spraying time of each raw material is controlled at 25 minutes, after the addition is completed, the mixture is obtained;
[0034] S3. Mix the obtained mixture with the weighed low liquid limit silt, add water and stir for 37.5 minutes to obtain the roadbed filler, and the water content of the roadbed filler is 12% to 15%.
[0035] The roadbed filler prepared in Example 1-Example 2 was evaluated by the uncon...